As reais razões do porque eu devo ser Ágil - Agile Tour São Paulo

Post on 01-Jul-2015

236 views 3 download

description

Introdução à metodotoligias ágeis,

Transcript of As reais razões do porque eu devo ser Ágil - Agile Tour São Paulo

Ruby on Rails

Coaching Consultoria

Planejamento

somos referência

9º projeto mais popular

250.000 views/mês

à venda na

Evolução

a tecnologia está evoluindo

e a maneira que fazemos software também...

Fonte: Standish Group, CHAOS Report

16%!

27%!26%!

28%!

34%!

29%!

35%!

32%!

37%!

1994! 1996! 1998! 2000! 2002! 2004! 2006! 2008! 2011!

Evolução da Taxa de Sucessoem Projetos de Software

mas ainda há

63%para avançar

O que causou esta melhora nos últimos 15 anos?

13

1970 1980 1990 2000 2010

70’s

15

Managing the development of large software systemsDr. Winston W. Royce (11 pages)

16

I SYSTE M

I ANALYSIS

PROGRAM DESIGN

I c o o , . o

TESTING

I OPERATIONS

Figure 2. Implementation steps to develop a large computer program for delivery to a customer.

I SYSTE M

I ANALYSIS

PROGRAM DESIGN

I c o o , . o

TESTING

I OPERATIONS

Figure 2. Implementation steps to develop a large computer program for delivery to a customer.

I believe in this concept, but the implementation described above is risky and invites failure. The problem is illustrated in Figure 4. The testing phase which occurs at the end of the development cycle is the first event for which timing, storage, input /output transfers, etc., are experienced as distinguished from analyzed. These phenomena are not precisely analyzable. They are not the solutions to the standard partial differential equations of mathematical physics for instance. Yet if these phenomena fail to satisfy the various external constraints, then invariably a major redesign is required. A simple octal patch or redo of some isolated code wil l not f ix these kinds of diff iculties. The required design changes are l ikely to be so disruptive that the software requirements upon which the design is based and which provides the rationale for everything are violated. Either the requirements must be modif ied, or a substantial change in the design is required. In effect the development process has returned to the origin and one can expect up to a lO0-percent overrun in schedule and/or costs.

One might note that there has been a skipping-over of the analysis and code phases. One cannot, of course, produce software wi thout these steps, but generally these phases are managed wi th relative ease and have l i tt le impact on requirements, design, and testing. In my experience there are whole departments consumed with the analysis of orbi t mechanics, spacecraft att i tude determination, mathematical opt imizat ion of payload activity and so forth, but when these departments have completed their di f f icul t and complex work, the resultant program steps involvea few lines of serial arithmetic code. If in the execution of their d i f f icul t and complex work the analysts have made a mistake, the correction is invariably implemented by a minor change in the code with no disruptive feedback into the other development bases.

However, I believe the illustrated approach to be fundamental ly sound. The remainder of this discussion presents five addit ional features that must be added to this basic approach to eliminate most of the development risks.

329

Engenharia de Software

heavy weight processes

80’s

Custo de mudança

21

Fase do projeto

Cus

to d

e M

udan

ça

a tentativa em 80’s...

23

1980’s

=Controlar Processos Reduzir Custos

TI orientada a Cu$to$

90’s

enfim, reforços...

forte adoção

ProgramaçãoOrientada a Objetos

surgem os primeiroslight weight processeslight

o resultado...

Custo de mudança

32

“Waterfall” (1970)

Novas abordagens 1990’s

Cus

to d

a M

udan

ça

Tempo

a conclusão...

34

1990’s

=Cicloscurtos

Entregas Constantes de Valor

TI orientada a Geração de Valor

2000’s

O Manifesto Ágil

Individuals and interactions over processes and tools

Fonte: http://agilemanifesto.org

Manifesto for Agile Software Development

We are uncovering better ways of developing software by doing it and helping others do it. Through this work we have come to value:

That is, while there is value in the items onthe right, we value the items on the left more.

Working software over comprehensive documentation

Customer collaboration over contract negotiation

Responding to change over following a plan

2010’s

duas realidadesem projetos...

realidade #1

equipesna realidade #1

equipe de especialistas

passagem de bastão = empurrar o problema

realidade #1

execução do projetona realidade #1

I SYSTE M

I ANALYSIS

PROGRAM DESIGN

I c o o , . o

TESTING

I OPERATIONS

Figure 2. Implementation steps to develop a large computer program for delivery to a customer.

I believe in this concept, but the implementation described above is risky and invites failure. The problem is illustrated in Figure 4. The testing phase which occurs at the end of the development cycle is the first event for which timing, storage, input /output transfers, etc., are experienced as distinguished from analyzed. These phenomena are not precisely analyzable. They are not the solutions to the standard partial differential equations of mathematical physics for instance. Yet if these phenomena fail to satisfy the various external constraints, then invariably a major redesign is required. A simple octal patch or redo of some isolated code wil l not f ix these kinds of diff iculties. The required design changes are l ikely to be so disruptive that the software requirements upon which the design is based and which provides the rationale for everything are violated. Either the requirements must be modif ied, or a substantial change in the design is required. In effect the development process has returned to the origin and one can expect up to a lO0-percent overrun in schedule and/or costs.

One might note that there has been a skipping-over of the analysis and code phases. One cannot, of course, produce software wi thout these steps, but generally these phases are managed wi th relative ease and have l i tt le impact on requirements, design, and testing. In my experience there are whole departments consumed with the analysis of orbi t mechanics, spacecraft att i tude determination, mathematical opt imizat ion of payload activity and so forth, but when these departments have completed their di f f icul t and complex work, the resultant program steps involvea few lines of serial arithmetic code. If in the execution of their d i f f icul t and complex work the analysts have made a mistake, the correction is invariably implemented by a minor change in the code with no disruptive feedback into the other development bases.

However, I believe the illustrated approach to be fundamental ly sound. The remainder of this discussion presents five addit ional features that must be added to this basic approach to eliminate most of the development risks.

329

requisitos mudam

não condiz com os requisitos

sempre atrasa

não há tempo

espero que funcione

realidade #1

realidade #1

ProblemasProblemas

Problemas

Problemas

Problemas

Problemas

Problemas

Problemas

Problemas

Problemas

Problemas

Problemas

Problemas

ProblemasProblemas

Problemas

Projeto

é tarde de mais!:(

lidando com mudançasna realidade #1

• processo lento e desgastante

• change requests

• adendo de contratos

• consome muito tempo e dinheiro

realidade #1

Custo de mudançaC

usto

da

Mud

ança

Tempo

realidade #1

entregasna realidade #1

Requisitos Design Coding IntegraçãoTestes Deploy

25%

% prontorealidade #1

0%

Projeto

Uso

2 meses de projeto

Entrega de Valor

Tempo

Valo

r E

ntre

gue

realidade #1

realidade #2

equipesna realidade #2

realidade #2

Times multi-disciplinaresformados por Generalistas Especialistas

execução do projetona realidade #2

realidade #2

I SYSTE M

I ANALYSIS

PROGRAM DESIGN

I c o o , . o

TESTING

I OPERATIONS

Figure 2. Implementation steps to develop a large computer program for delivery to a customer.

I believe in this concept, but the implementation described above is risky and invites failure. The problem is illustrated in Figure 4. The testing phase which occurs at the end of the development cycle is the first event for which timing, storage, input /output transfers, etc., are experienced as distinguished from analyzed. These phenomena are not precisely analyzable. They are not the solutions to the standard partial differential equations of mathematical physics for instance. Yet if these phenomena fail to satisfy the various external constraints, then invariably a major redesign is required. A simple octal patch or redo of some isolated code wil l not f ix these kinds of diff iculties. The required design changes are l ikely to be so disruptive that the software requirements upon which the design is based and which provides the rationale for everything are violated. Either the requirements must be modif ied, or a substantial change in the design is required. In effect the development process has returned to the origin and one can expect up to a lO0-percent overrun in schedule and/or costs.

One might note that there has been a skipping-over of the analysis and code phases. One cannot, of course, produce software wi thout these steps, but generally these phases are managed wi th relative ease and have l i tt le impact on requirements, design, and testing. In my experience there are whole departments consumed with the analysis of orbi t mechanics, spacecraft att i tude determination, mathematical opt imizat ion of payload activity and so forth, but when these departments have completed their di f f icul t and complex work, the resultant program steps involvea few lines of serial arithmetic code. If in the execution of their d i f f icul t and complex work the analysts have made a mistake, the correction is invariably implemented by a minor change in the code with no disruptive feedback into the other development bases.

However, I believe the illustrated approach to be fundamental ly sound. The remainder of this discussion presents five addit ional features that must be added to this basic approach to eliminate most of the development risks.

329

I SYSTE M

I ANALYSIS

PROGRAM DESIGN

I c o o , . o

TESTING

I OPERATIONS

Figure 2. Implementation steps to develop a large computer program for delivery to a customer.

I believe in this concept, but the implementation described above is risky and invites failure. The problem is illustrated in Figure 4. The testing phase which occurs at the end of the development cycle is the first event for which timing, storage, input /output transfers, etc., are experienced as distinguished from analyzed. These phenomena are not precisely analyzable. They are not the solutions to the standard partial differential equations of mathematical physics for instance. Yet if these phenomena fail to satisfy the various external constraints, then invariably a major redesign is required. A simple octal patch or redo of some isolated code wil l not f ix these kinds of diff iculties. The required design changes are l ikely to be so disruptive that the software requirements upon which the design is based and which provides the rationale for everything are violated. Either the requirements must be modif ied, or a substantial change in the design is required. In effect the development process has returned to the origin and one can expect up to a lO0-percent overrun in schedule and/or costs.

One might note that there has been a skipping-over of the analysis and code phases. One cannot, of course, produce software wi thout these steps, but generally these phases are managed wi th relative ease and have l i tt le impact on requirements, design, and testing. In my experience there are whole departments consumed with the analysis of orbi t mechanics, spacecraft att i tude determination, mathematical opt imizat ion of payload activity and so forth, but when these departments have completed their di f f icul t and complex work, the resultant program steps involvea few lines of serial arithmetic code. If in the execution of their d i f f icul t and complex work the analysts have made a mistake, the correction is invariably implemented by a minor change in the code with no disruptive feedback into the other development bases.

However, I believe the illustrated approach to be fundamental ly sound. The remainder of this discussion presents five addit ional features that must be added to this basic approach to eliminate most of the development risks.

329

I SYSTE M

I ANALYSIS

PROGRAM DESIGN

I c o o , . o

TESTING

I OPERATIONS

Figure 2. Implementation steps to develop a large computer program for delivery to a customer.

I believe in this concept, but the implementation described above is risky and invites failure. The problem is illustrated in Figure 4. The testing phase which occurs at the end of the development cycle is the first event for which timing, storage, input /output transfers, etc., are experienced as distinguished from analyzed. These phenomena are not precisely analyzable. They are not the solutions to the standard partial differential equations of mathematical physics for instance. Yet if these phenomena fail to satisfy the various external constraints, then invariably a major redesign is required. A simple octal patch or redo of some isolated code wil l not f ix these kinds of diff iculties. The required design changes are l ikely to be so disruptive that the software requirements upon which the design is based and which provides the rationale for everything are violated. Either the requirements must be modif ied, or a substantial change in the design is required. In effect the development process has returned to the origin and one can expect up to a lO0-percent overrun in schedule and/or costs.

One might note that there has been a skipping-over of the analysis and code phases. One cannot, of course, produce software wi thout these steps, but generally these phases are managed wi th relative ease and have l i tt le impact on requirements, design, and testing. In my experience there are whole departments consumed with the analysis of orbi t mechanics, spacecraft att i tude determination, mathematical opt imizat ion of payload activity and so forth, but when these departments have completed their di f f icul t and complex work, the resultant program steps involvea few lines of serial arithmetic code. If in the execution of their d i f f icul t and complex work the analysts have made a mistake, the correction is invariably implemented by a minor change in the code with no disruptive feedback into the other development bases.

However, I believe the illustrated approach to be fundamental ly sound. The remainder of this discussion presents five addit ional features that must be added to this basic approach to eliminate most of the development risks.

329

I SYSTE M

I ANALYSIS

PROGRAM DESIGN

I c o o , . o

TESTING

I OPERATIONS

Figure 2. Implementation steps to develop a large computer program for delivery to a customer.

I believe in this concept, but the implementation described above is risky and invites failure. The problem is illustrated in Figure 4. The testing phase which occurs at the end of the development cycle is the first event for which timing, storage, input /output transfers, etc., are experienced as distinguished from analyzed. These phenomena are not precisely analyzable. They are not the solutions to the standard partial differential equations of mathematical physics for instance. Yet if these phenomena fail to satisfy the various external constraints, then invariably a major redesign is required. A simple octal patch or redo of some isolated code wil l not f ix these kinds of diff iculties. The required design changes are l ikely to be so disruptive that the software requirements upon which the design is based and which provides the rationale for everything are violated. Either the requirements must be modif ied, or a substantial change in the design is required. In effect the development process has returned to the origin and one can expect up to a lO0-percent overrun in schedule and/or costs.

One might note that there has been a skipping-over of the analysis and code phases. One cannot, of course, produce software wi thout these steps, but generally these phases are managed wi th relative ease and have l i tt le impact on requirements, design, and testing. In my experience there are whole departments consumed with the analysis of orbi t mechanics, spacecraft att i tude determination, mathematical opt imizat ion of payload activity and so forth, but when these departments have completed their di f f icul t and complex work, the resultant program steps involvea few lines of serial arithmetic code. If in the execution of their d i f f icul t and complex work the analysts have made a mistake, the correction is invariably implemented by a minor change in the code with no disruptive feedback into the other development bases.

However, I believe the illustrated approach to be fundamental ly sound. The remainder of this discussion presents five addit ional features that must be added to this basic approach to eliminate most of the development risks.

329

I SYSTE M

I ANALYSIS

PROGRAM DESIGN

I c o o , . o

TESTING

I OPERATIONS

Figure 2. Implementation steps to develop a large computer program for delivery to a customer.

I believe in this concept, but the implementation described above is risky and invites failure. The problem is illustrated in Figure 4. The testing phase which occurs at the end of the development cycle is the first event for which timing, storage, input /output transfers, etc., are experienced as distinguished from analyzed. These phenomena are not precisely analyzable. They are not the solutions to the standard partial differential equations of mathematical physics for instance. Yet if these phenomena fail to satisfy the various external constraints, then invariably a major redesign is required. A simple octal patch or redo of some isolated code wil l not f ix these kinds of diff iculties. The required design changes are l ikely to be so disruptive that the software requirements upon which the design is based and which provides the rationale for everything are violated. Either the requirements must be modif ied, or a substantial change in the design is required. In effect the development process has returned to the origin and one can expect up to a lO0-percent overrun in schedule and/or costs.

One might note that there has been a skipping-over of the analysis and code phases. One cannot, of course, produce software wi thout these steps, but generally these phases are managed wi th relative ease and have l i tt le impact on requirements, design, and testing. In my experience there are whole departments consumed with the analysis of orbi t mechanics, spacecraft att i tude determination, mathematical opt imizat ion of payload activity and so forth, but when these departments have completed their di f f icul t and complex work, the resultant program steps involvea few lines of serial arithmetic code. If in the execution of their d i f f icul t and complex work the analysts have made a mistake, the correction is invariably implemented by a minor change in the code with no disruptive feedback into the other development bases.

However, I believe the illustrated approach to be fundamental ly sound. The remainder of this discussion presents five addit ional features that must be added to this basic approach to eliminate most of the development risks.

329

I SYSTE M

I ANALYSIS

PROGRAM DESIGN

I c o o , . o

TESTING

I OPERATIONS

Figure 2. Implementation steps to develop a large computer program for delivery to a customer.

I believe in this concept, but the implementation described above is risky and invites failure. The problem is illustrated in Figure 4. The testing phase which occurs at the end of the development cycle is the first event for which timing, storage, input /output transfers, etc., are experienced as distinguished from analyzed. These phenomena are not precisely analyzable. They are not the solutions to the standard partial differential equations of mathematical physics for instance. Yet if these phenomena fail to satisfy the various external constraints, then invariably a major redesign is required. A simple octal patch or redo of some isolated code wil l not f ix these kinds of diff iculties. The required design changes are l ikely to be so disruptive that the software requirements upon which the design is based and which provides the rationale for everything are violated. Either the requirements must be modif ied, or a substantial change in the design is required. In effect the development process has returned to the origin and one can expect up to a lO0-percent overrun in schedule and/or costs.

One might note that there has been a skipping-over of the analysis and code phases. One cannot, of course, produce software wi thout these steps, but generally these phases are managed wi th relative ease and have l i tt le impact on requirements, design, and testing. In my experience there are whole departments consumed with the analysis of orbi t mechanics, spacecraft att i tude determination, mathematical opt imizat ion of payload activity and so forth, but when these departments have completed their di f f icul t and complex work, the resultant program steps involvea few lines of serial arithmetic code. If in the execution of their d i f f icul t and complex work the analysts have made a mistake, the correction is invariably implemented by a minor change in the code with no disruptive feedback into the other development bases.

However, I believe the illustrated approach to be fundamental ly sound. The remainder of this discussion presents five addit ional features that must be added to this basic approach to eliminate most of the development risks.

329

I SYSTE M

I ANALYSIS

PROGRAM DESIGN

I c o o , . o

TESTING

I OPERATIONS

Figure 2. Implementation steps to develop a large computer program for delivery to a customer.

I believe in this concept, but the implementation described above is risky and invites failure. The problem is illustrated in Figure 4. The testing phase which occurs at the end of the development cycle is the first event for which timing, storage, input /output transfers, etc., are experienced as distinguished from analyzed. These phenomena are not precisely analyzable. They are not the solutions to the standard partial differential equations of mathematical physics for instance. Yet if these phenomena fail to satisfy the various external constraints, then invariably a major redesign is required. A simple octal patch or redo of some isolated code wil l not f ix these kinds of diff iculties. The required design changes are l ikely to be so disruptive that the software requirements upon which the design is based and which provides the rationale for everything are violated. Either the requirements must be modif ied, or a substantial change in the design is required. In effect the development process has returned to the origin and one can expect up to a lO0-percent overrun in schedule and/or costs.

One might note that there has been a skipping-over of the analysis and code phases. One cannot, of course, produce software wi thout these steps, but generally these phases are managed wi th relative ease and have l i tt le impact on requirements, design, and testing. In my experience there are whole departments consumed with the analysis of orbi t mechanics, spacecraft att i tude determination, mathematical opt imizat ion of payload activity and so forth, but when these departments have completed their di f f icul t and complex work, the resultant program steps involvea few lines of serial arithmetic code. If in the execution of their d i f f icul t and complex work the analysts have made a mistake, the correction is invariably implemented by a minor change in the code with no disruptive feedback into the other development bases.

However, I believe the illustrated approach to be fundamental ly sound. The remainder of this discussion presents five addit ional features that must be added to this basic approach to eliminate most of the development risks.

329

Sprint 1I SYSTE M

I ANALYSIS

PROGRAM DESIGN

I c o o , . o

TESTING

I OPERATIONS

Figure 2. Implementation steps to develop a large computer program for delivery to a customer.

I believe in this concept, but the implementation described above is risky and invites failure. The problem is illustrated in Figure 4. The testing phase which occurs at the end of the development cycle is the first event for which timing, storage, input /output transfers, etc., are experienced as distinguished from analyzed. These phenomena are not precisely analyzable. They are not the solutions to the standard partial differential equations of mathematical physics for instance. Yet if these phenomena fail to satisfy the various external constraints, then invariably a major redesign is required. A simple octal patch or redo of some isolated code wil l not f ix these kinds of diff iculties. The required design changes are l ikely to be so disruptive that the software requirements upon which the design is based and which provides the rationale for everything are violated. Either the requirements must be modif ied, or a substantial change in the design is required. In effect the development process has returned to the origin and one can expect up to a lO0-percent overrun in schedule and/or costs.

One might note that there has been a skipping-over of the analysis and code phases. One cannot, of course, produce software wi thout these steps, but generally these phases are managed wi th relative ease and have l i tt le impact on requirements, design, and testing. In my experience there are whole departments consumed with the analysis of orbi t mechanics, spacecraft att i tude determination, mathematical opt imizat ion of payload activity and so forth, but when these departments have completed their di f f icul t and complex work, the resultant program steps involvea few lines of serial arithmetic code. If in the execution of their d i f f icul t and complex work the analysts have made a mistake, the correction is invariably implemented by a minor change in the code with no disruptive feedback into the other development bases.

However, I believe the illustrated approach to be fundamental ly sound. The remainder of this discussion presents five addit ional features that must be added to this basic approach to eliminate most of the development risks.

329

I SYSTE M

I ANALYSIS

PROGRAM DESIGN

I c o o , . o

TESTING

I OPERATIONS

Figure 2. Implementation steps to develop a large computer program for delivery to a customer.

I believe in this concept, but the implementation described above is risky and invites failure. The problem is illustrated in Figure 4. The testing phase which occurs at the end of the development cycle is the first event for which timing, storage, input /output transfers, etc., are experienced as distinguished from analyzed. These phenomena are not precisely analyzable. They are not the solutions to the standard partial differential equations of mathematical physics for instance. Yet if these phenomena fail to satisfy the various external constraints, then invariably a major redesign is required. A simple octal patch or redo of some isolated code wil l not f ix these kinds of diff iculties. The required design changes are l ikely to be so disruptive that the software requirements upon which the design is based and which provides the rationale for everything are violated. Either the requirements must be modif ied, or a substantial change in the design is required. In effect the development process has returned to the origin and one can expect up to a lO0-percent overrun in schedule and/or costs.

One might note that there has been a skipping-over of the analysis and code phases. One cannot, of course, produce software wi thout these steps, but generally these phases are managed wi th relative ease and have l i tt le impact on requirements, design, and testing. In my experience there are whole departments consumed with the analysis of orbi t mechanics, spacecraft att i tude determination, mathematical opt imizat ion of payload activity and so forth, but when these departments have completed their di f f icul t and complex work, the resultant program steps involvea few lines of serial arithmetic code. If in the execution of their d i f f icul t and complex work the analysts have made a mistake, the correction is invariably implemented by a minor change in the code with no disruptive feedback into the other development bases.

However, I believe the illustrated approach to be fundamental ly sound. The remainder of this discussion presents five addit ional features that must be added to this basic approach to eliminate most of the development risks.

329

I SYSTE M

I ANALYSIS

PROGRAM DESIGN

I c o o , . o

TESTING

I OPERATIONS

Figure 2. Implementation steps to develop a large computer program for delivery to a customer.

I believe in this concept, but the implementation described above is risky and invites failure. The problem is illustrated in Figure 4. The testing phase which occurs at the end of the development cycle is the first event for which timing, storage, input /output transfers, etc., are experienced as distinguished from analyzed. These phenomena are not precisely analyzable. They are not the solutions to the standard partial differential equations of mathematical physics for instance. Yet if these phenomena fail to satisfy the various external constraints, then invariably a major redesign is required. A simple octal patch or redo of some isolated code wil l not f ix these kinds of diff iculties. The required design changes are l ikely to be so disruptive that the software requirements upon which the design is based and which provides the rationale for everything are violated. Either the requirements must be modif ied, or a substantial change in the design is required. In effect the development process has returned to the origin and one can expect up to a lO0-percent overrun in schedule and/or costs.

One might note that there has been a skipping-over of the analysis and code phases. One cannot, of course, produce software wi thout these steps, but generally these phases are managed wi th relative ease and have l i tt le impact on requirements, design, and testing. In my experience there are whole departments consumed with the analysis of orbi t mechanics, spacecraft att i tude determination, mathematical opt imizat ion of payload activity and so forth, but when these departments have completed their di f f icul t and complex work, the resultant program steps involvea few lines of serial arithmetic code. If in the execution of their d i f f icul t and complex work the analysts have made a mistake, the correction is invariably implemented by a minor change in the code with no disruptive feedback into the other development bases.

However, I believe the illustrated approach to be fundamental ly sound. The remainder of this discussion presents five addit ional features that must be added to this basic approach to eliminate most of the development risks.

329

I SYSTE M

I ANALYSIS

PROGRAM DESIGN

I c o o , . o

TESTING

I OPERATIONS

Figure 2. Implementation steps to develop a large computer program for delivery to a customer.

I believe in this concept, but the implementation described above is risky and invites failure. The problem is illustrated in Figure 4. The testing phase which occurs at the end of the development cycle is the first event for which timing, storage, input /output transfers, etc., are experienced as distinguished from analyzed. These phenomena are not precisely analyzable. They are not the solutions to the standard partial differential equations of mathematical physics for instance. Yet if these phenomena fail to satisfy the various external constraints, then invariably a major redesign is required. A simple octal patch or redo of some isolated code wil l not f ix these kinds of diff iculties. The required design changes are l ikely to be so disruptive that the software requirements upon which the design is based and which provides the rationale for everything are violated. Either the requirements must be modif ied, or a substantial change in the design is required. In effect the development process has returned to the origin and one can expect up to a lO0-percent overrun in schedule and/or costs.

One might note that there has been a skipping-over of the analysis and code phases. One cannot, of course, produce software wi thout these steps, but generally these phases are managed wi th relative ease and have l i tt le impact on requirements, design, and testing. In my experience there are whole departments consumed with the analysis of orbi t mechanics, spacecraft att i tude determination, mathematical opt imizat ion of payload activity and so forth, but when these departments have completed their di f f icul t and complex work, the resultant program steps involvea few lines of serial arithmetic code. If in the execution of their d i f f icul t and complex work the analysts have made a mistake, the correction is invariably implemented by a minor change in the code with no disruptive feedback into the other development bases.

However, I believe the illustrated approach to be fundamental ly sound. The remainder of this discussion presents five addit ional features that must be added to this basic approach to eliminate most of the development risks.

329

I SYSTE M

I ANALYSIS

PROGRAM DESIGN

I c o o , . o

TESTING

I OPERATIONS

Figure 2. Implementation steps to develop a large computer program for delivery to a customer.

I believe in this concept, but the implementation described above is risky and invites failure. The problem is illustrated in Figure 4. The testing phase which occurs at the end of the development cycle is the first event for which timing, storage, input /output transfers, etc., are experienced as distinguished from analyzed. These phenomena are not precisely analyzable. They are not the solutions to the standard partial differential equations of mathematical physics for instance. Yet if these phenomena fail to satisfy the various external constraints, then invariably a major redesign is required. A simple octal patch or redo of some isolated code wil l not f ix these kinds of diff iculties. The required design changes are l ikely to be so disruptive that the software requirements upon which the design is based and which provides the rationale for everything are violated. Either the requirements must be modif ied, or a substantial change in the design is required. In effect the development process has returned to the origin and one can expect up to a lO0-percent overrun in schedule and/or costs.

One might note that there has been a skipping-over of the analysis and code phases. One cannot, of course, produce software wi thout these steps, but generally these phases are managed wi th relative ease and have l i tt le impact on requirements, design, and testing. In my experience there are whole departments consumed with the analysis of orbi t mechanics, spacecraft att i tude determination, mathematical opt imizat ion of payload activity and so forth, but when these departments have completed their di f f icul t and complex work, the resultant program steps involvea few lines of serial arithmetic code. If in the execution of their d i f f icul t and complex work the analysts have made a mistake, the correction is invariably implemented by a minor change in the code with no disruptive feedback into the other development bases.

However, I believe the illustrated approach to be fundamental ly sound. The remainder of this discussion presents five addit ional features that must be added to this basic approach to eliminate most of the development risks.

329

I SYSTE M

I ANALYSIS

PROGRAM DESIGN

I c o o , . o

TESTING

I OPERATIONS

Figure 2. Implementation steps to develop a large computer program for delivery to a customer.

I believe in this concept, but the implementation described above is risky and invites failure. The problem is illustrated in Figure 4. The testing phase which occurs at the end of the development cycle is the first event for which timing, storage, input /output transfers, etc., are experienced as distinguished from analyzed. These phenomena are not precisely analyzable. They are not the solutions to the standard partial differential equations of mathematical physics for instance. Yet if these phenomena fail to satisfy the various external constraints, then invariably a major redesign is required. A simple octal patch or redo of some isolated code wil l not f ix these kinds of diff iculties. The required design changes are l ikely to be so disruptive that the software requirements upon which the design is based and which provides the rationale for everything are violated. Either the requirements must be modif ied, or a substantial change in the design is required. In effect the development process has returned to the origin and one can expect up to a lO0-percent overrun in schedule and/or costs.

One might note that there has been a skipping-over of the analysis and code phases. One cannot, of course, produce software wi thout these steps, but generally these phases are managed wi th relative ease and have l i tt le impact on requirements, design, and testing. In my experience there are whole departments consumed with the analysis of orbi t mechanics, spacecraft att i tude determination, mathematical opt imizat ion of payload activity and so forth, but when these departments have completed their di f f icul t and complex work, the resultant program steps involvea few lines of serial arithmetic code. If in the execution of their d i f f icul t and complex work the analysts have made a mistake, the correction is invariably implemented by a minor change in the code with no disruptive feedback into the other development bases.

However, I believe the illustrated approach to be fundamental ly sound. The remainder of this discussion presents five addit ional features that must be added to this basic approach to eliminate most of the development risks.

329

I SYSTE M

I ANALYSIS

PROGRAM DESIGN

I c o o , . o

TESTING

I OPERATIONS

Figure 2. Implementation steps to develop a large computer program for delivery to a customer.

I believe in this concept, but the implementation described above is risky and invites failure. The problem is illustrated in Figure 4. The testing phase which occurs at the end of the development cycle is the first event for which timing, storage, input /output transfers, etc., are experienced as distinguished from analyzed. These phenomena are not precisely analyzable. They are not the solutions to the standard partial differential equations of mathematical physics for instance. Yet if these phenomena fail to satisfy the various external constraints, then invariably a major redesign is required. A simple octal patch or redo of some isolated code wil l not f ix these kinds of diff iculties. The required design changes are l ikely to be so disruptive that the software requirements upon which the design is based and which provides the rationale for everything are violated. Either the requirements must be modif ied, or a substantial change in the design is required. In effect the development process has returned to the origin and one can expect up to a lO0-percent overrun in schedule and/or costs.

One might note that there has been a skipping-over of the analysis and code phases. One cannot, of course, produce software wi thout these steps, but generally these phases are managed wi th relative ease and have l i tt le impact on requirements, design, and testing. In my experience there are whole departments consumed with the analysis of orbi t mechanics, spacecraft att i tude determination, mathematical opt imizat ion of payload activity and so forth, but when these departments have completed their di f f icul t and complex work, the resultant program steps involvea few lines of serial arithmetic code. If in the execution of their d i f f icul t and complex work the analysts have made a mistake, the correction is invariably implemented by a minor change in the code with no disruptive feedback into the other development bases.

However, I believe the illustrated approach to be fundamental ly sound. The remainder of this discussion presents five addit ional features that must be added to this basic approach to eliminate most of the development risks.

329

Sprint 2I SYSTE M

I ANALYSIS

PROGRAM DESIGN

I c o o , . o

TESTING

I OPERATIONS

Figure 2. Implementation steps to develop a large computer program for delivery to a customer.

I believe in this concept, but the implementation described above is risky and invites failure. The problem is illustrated in Figure 4. The testing phase which occurs at the end of the development cycle is the first event for which timing, storage, input /output transfers, etc., are experienced as distinguished from analyzed. These phenomena are not precisely analyzable. They are not the solutions to the standard partial differential equations of mathematical physics for instance. Yet if these phenomena fail to satisfy the various external constraints, then invariably a major redesign is required. A simple octal patch or redo of some isolated code wil l not f ix these kinds of diff iculties. The required design changes are l ikely to be so disruptive that the software requirements upon which the design is based and which provides the rationale for everything are violated. Either the requirements must be modif ied, or a substantial change in the design is required. In effect the development process has returned to the origin and one can expect up to a lO0-percent overrun in schedule and/or costs.

One might note that there has been a skipping-over of the analysis and code phases. One cannot, of course, produce software wi thout these steps, but generally these phases are managed wi th relative ease and have l i tt le impact on requirements, design, and testing. In my experience there are whole departments consumed with the analysis of orbi t mechanics, spacecraft att i tude determination, mathematical opt imizat ion of payload activity and so forth, but when these departments have completed their di f f icul t and complex work, the resultant program steps involvea few lines of serial arithmetic code. If in the execution of their d i f f icul t and complex work the analysts have made a mistake, the correction is invariably implemented by a minor change in the code with no disruptive feedback into the other development bases.

However, I believe the illustrated approach to be fundamental ly sound. The remainder of this discussion presents five addit ional features that must be added to this basic approach to eliminate most of the development risks.

329

I SYSTE M

I ANALYSIS

PROGRAM DESIGN

I c o o , . o

TESTING

I OPERATIONS

Figure 2. Implementation steps to develop a large computer program for delivery to a customer.

I believe in this concept, but the implementation described above is risky and invites failure. The problem is illustrated in Figure 4. The testing phase which occurs at the end of the development cycle is the first event for which timing, storage, input /output transfers, etc., are experienced as distinguished from analyzed. These phenomena are not precisely analyzable. They are not the solutions to the standard partial differential equations of mathematical physics for instance. Yet if these phenomena fail to satisfy the various external constraints, then invariably a major redesign is required. A simple octal patch or redo of some isolated code wil l not f ix these kinds of diff iculties. The required design changes are l ikely to be so disruptive that the software requirements upon which the design is based and which provides the rationale for everything are violated. Either the requirements must be modif ied, or a substantial change in the design is required. In effect the development process has returned to the origin and one can expect up to a lO0-percent overrun in schedule and/or costs.

One might note that there has been a skipping-over of the analysis and code phases. One cannot, of course, produce software wi thout these steps, but generally these phases are managed wi th relative ease and have l i tt le impact on requirements, design, and testing. In my experience there are whole departments consumed with the analysis of orbi t mechanics, spacecraft att i tude determination, mathematical opt imizat ion of payload activity and so forth, but when these departments have completed their di f f icul t and complex work, the resultant program steps involvea few lines of serial arithmetic code. If in the execution of their d i f f icul t and complex work the analysts have made a mistake, the correction is invariably implemented by a minor change in the code with no disruptive feedback into the other development bases.

However, I believe the illustrated approach to be fundamental ly sound. The remainder of this discussion presents five addit ional features that must be added to this basic approach to eliminate most of the development risks.

329

I SYSTE M

I ANALYSIS

PROGRAM DESIGN

I c o o , . o

TESTING

I OPERATIONS

Figure 2. Implementation steps to develop a large computer program for delivery to a customer.

I believe in this concept, but the implementation described above is risky and invites failure. The problem is illustrated in Figure 4. The testing phase which occurs at the end of the development cycle is the first event for which timing, storage, input /output transfers, etc., are experienced as distinguished from analyzed. These phenomena are not precisely analyzable. They are not the solutions to the standard partial differential equations of mathematical physics for instance. Yet if these phenomena fail to satisfy the various external constraints, then invariably a major redesign is required. A simple octal patch or redo of some isolated code wil l not f ix these kinds of diff iculties. The required design changes are l ikely to be so disruptive that the software requirements upon which the design is based and which provides the rationale for everything are violated. Either the requirements must be modif ied, or a substantial change in the design is required. In effect the development process has returned to the origin and one can expect up to a lO0-percent overrun in schedule and/or costs.

One might note that there has been a skipping-over of the analysis and code phases. One cannot, of course, produce software wi thout these steps, but generally these phases are managed wi th relative ease and have l i tt le impact on requirements, design, and testing. In my experience there are whole departments consumed with the analysis of orbi t mechanics, spacecraft att i tude determination, mathematical opt imizat ion of payload activity and so forth, but when these departments have completed their di f f icul t and complex work, the resultant program steps involvea few lines of serial arithmetic code. If in the execution of their d i f f icul t and complex work the analysts have made a mistake, the correction is invariably implemented by a minor change in the code with no disruptive feedback into the other development bases.

However, I believe the illustrated approach to be fundamental ly sound. The remainder of this discussion presents five addit ional features that must be added to this basic approach to eliminate most of the development risks.

329

I SYSTE M

I ANALYSIS

PROGRAM DESIGN

I c o o , . o

TESTING

I OPERATIONS

Figure 2. Implementation steps to develop a large computer program for delivery to a customer.

I believe in this concept, but the implementation described above is risky and invites failure. The problem is illustrated in Figure 4. The testing phase which occurs at the end of the development cycle is the first event for which timing, storage, input /output transfers, etc., are experienced as distinguished from analyzed. These phenomena are not precisely analyzable. They are not the solutions to the standard partial differential equations of mathematical physics for instance. Yet if these phenomena fail to satisfy the various external constraints, then invariably a major redesign is required. A simple octal patch or redo of some isolated code wil l not f ix these kinds of diff iculties. The required design changes are l ikely to be so disruptive that the software requirements upon which the design is based and which provides the rationale for everything are violated. Either the requirements must be modif ied, or a substantial change in the design is required. In effect the development process has returned to the origin and one can expect up to a lO0-percent overrun in schedule and/or costs.

One might note that there has been a skipping-over of the analysis and code phases. One cannot, of course, produce software wi thout these steps, but generally these phases are managed wi th relative ease and have l i tt le impact on requirements, design, and testing. In my experience there are whole departments consumed with the analysis of orbi t mechanics, spacecraft att i tude determination, mathematical opt imizat ion of payload activity and so forth, but when these departments have completed their di f f icul t and complex work, the resultant program steps involvea few lines of serial arithmetic code. If in the execution of their d i f f icul t and complex work the analysts have made a mistake, the correction is invariably implemented by a minor change in the code with no disruptive feedback into the other development bases.

However, I believe the illustrated approach to be fundamental ly sound. The remainder of this discussion presents five addit ional features that must be added to this basic approach to eliminate most of the development risks.

329

I SYSTE M

I ANALYSIS

PROGRAM DESIGN

I c o o , . o

TESTING

I OPERATIONS

Figure 2. Implementation steps to develop a large computer program for delivery to a customer.

I believe in this concept, but the implementation described above is risky and invites failure. The problem is illustrated in Figure 4. The testing phase which occurs at the end of the development cycle is the first event for which timing, storage, input /output transfers, etc., are experienced as distinguished from analyzed. These phenomena are not precisely analyzable. They are not the solutions to the standard partial differential equations of mathematical physics for instance. Yet if these phenomena fail to satisfy the various external constraints, then invariably a major redesign is required. A simple octal patch or redo of some isolated code wil l not f ix these kinds of diff iculties. The required design changes are l ikely to be so disruptive that the software requirements upon which the design is based and which provides the rationale for everything are violated. Either the requirements must be modif ied, or a substantial change in the design is required. In effect the development process has returned to the origin and one can expect up to a lO0-percent overrun in schedule and/or costs.

One might note that there has been a skipping-over of the analysis and code phases. One cannot, of course, produce software wi thout these steps, but generally these phases are managed wi th relative ease and have l i tt le impact on requirements, design, and testing. In my experience there are whole departments consumed with the analysis of orbi t mechanics, spacecraft att i tude determination, mathematical opt imizat ion of payload activity and so forth, but when these departments have completed their di f f icul t and complex work, the resultant program steps involvea few lines of serial arithmetic code. If in the execution of their d i f f icul t and complex work the analysts have made a mistake, the correction is invariably implemented by a minor change in the code with no disruptive feedback into the other development bases.

However, I believe the illustrated approach to be fundamental ly sound. The remainder of this discussion presents five addit ional features that must be added to this basic approach to eliminate most of the development risks.

329

I SYSTE M

I ANALYSIS

PROGRAM DESIGN

I c o o , . o

TESTING

I OPERATIONS

Figure 2. Implementation steps to develop a large computer program for delivery to a customer.

I believe in this concept, but the implementation described above is risky and invites failure. The problem is illustrated in Figure 4. The testing phase which occurs at the end of the development cycle is the first event for which timing, storage, input /output transfers, etc., are experienced as distinguished from analyzed. These phenomena are not precisely analyzable. They are not the solutions to the standard partial differential equations of mathematical physics for instance. Yet if these phenomena fail to satisfy the various external constraints, then invariably a major redesign is required. A simple octal patch or redo of some isolated code wil l not f ix these kinds of diff iculties. The required design changes are l ikely to be so disruptive that the software requirements upon which the design is based and which provides the rationale for everything are violated. Either the requirements must be modif ied, or a substantial change in the design is required. In effect the development process has returned to the origin and one can expect up to a lO0-percent overrun in schedule and/or costs.

One might note that there has been a skipping-over of the analysis and code phases. One cannot, of course, produce software wi thout these steps, but generally these phases are managed wi th relative ease and have l i tt le impact on requirements, design, and testing. In my experience there are whole departments consumed with the analysis of orbi t mechanics, spacecraft att i tude determination, mathematical opt imizat ion of payload activity and so forth, but when these departments have completed their di f f icul t and complex work, the resultant program steps involvea few lines of serial arithmetic code. If in the execution of their d i f f icul t and complex work the analysts have made a mistake, the correction is invariably implemented by a minor change in the code with no disruptive feedback into the other development bases.

However, I believe the illustrated approach to be fundamental ly sound. The remainder of this discussion presents five addit ional features that must be added to this basic approach to eliminate most of the development risks.

329

I SYSTE M

I ANALYSIS

PROGRAM DESIGN

I c o o , . o

TESTING

I OPERATIONS

Figure 2. Implementation steps to develop a large computer program for delivery to a customer.

I believe in this concept, but the implementation described above is risky and invites failure. The problem is illustrated in Figure 4. The testing phase which occurs at the end of the development cycle is the first event for which timing, storage, input /output transfers, etc., are experienced as distinguished from analyzed. These phenomena are not precisely analyzable. They are not the solutions to the standard partial differential equations of mathematical physics for instance. Yet if these phenomena fail to satisfy the various external constraints, then invariably a major redesign is required. A simple octal patch or redo of some isolated code wil l not f ix these kinds of diff iculties. The required design changes are l ikely to be so disruptive that the software requirements upon which the design is based and which provides the rationale for everything are violated. Either the requirements must be modif ied, or a substantial change in the design is required. In effect the development process has returned to the origin and one can expect up to a lO0-percent overrun in schedule and/or costs.

One might note that there has been a skipping-over of the analysis and code phases. One cannot, of course, produce software wi thout these steps, but generally these phases are managed wi th relative ease and have l i tt le impact on requirements, design, and testing. In my experience there are whole departments consumed with the analysis of orbi t mechanics, spacecraft att i tude determination, mathematical opt imizat ion of payload activity and so forth, but when these departments have completed their di f f icul t and complex work, the resultant program steps involvea few lines of serial arithmetic code. If in the execution of their d i f f icul t and complex work the analysts have made a mistake, the correction is invariably implemented by a minor change in the code with no disruptive feedback into the other development bases.

However, I believe the illustrated approach to be fundamental ly sound. The remainder of this discussion presents five addit ional features that must be added to this basic approach to eliminate most of the development risks.

329

Sprint ...I SYSTE M

I ANALYSIS

PROGRAM DESIGN

I c o o , . o

TESTING

I OPERATIONS

Figure 2. Implementation steps to develop a large computer program for delivery to a customer.

I believe in this concept, but the implementation described above is risky and invites failure. The problem is illustrated in Figure 4. The testing phase which occurs at the end of the development cycle is the first event for which timing, storage, input /output transfers, etc., are experienced as distinguished from analyzed. These phenomena are not precisely analyzable. They are not the solutions to the standard partial differential equations of mathematical physics for instance. Yet if these phenomena fail to satisfy the various external constraints, then invariably a major redesign is required. A simple octal patch or redo of some isolated code wil l not f ix these kinds of diff iculties. The required design changes are l ikely to be so disruptive that the software requirements upon which the design is based and which provides the rationale for everything are violated. Either the requirements must be modif ied, or a substantial change in the design is required. In effect the development process has returned to the origin and one can expect up to a lO0-percent overrun in schedule and/or costs.

One might note that there has been a skipping-over of the analysis and code phases. One cannot, of course, produce software wi thout these steps, but generally these phases are managed wi th relative ease and have l i tt le impact on requirements, design, and testing. In my experience there are whole departments consumed with the analysis of orbi t mechanics, spacecraft att i tude determination, mathematical opt imizat ion of payload activity and so forth, but when these departments have completed their di f f icul t and complex work, the resultant program steps involvea few lines of serial arithmetic code. If in the execution of their d i f f icul t and complex work the analysts have made a mistake, the correction is invariably implemented by a minor change in the code with no disruptive feedback into the other development bases.

However, I believe the illustrated approach to be fundamental ly sound. The remainder of this discussion presents five addit ional features that must be added to this basic approach to eliminate most of the development risks.

329

I SYSTE M

I ANALYSIS

PROGRAM DESIGN

I c o o , . o

TESTING

I OPERATIONS

Figure 2. Implementation steps to develop a large computer program for delivery to a customer.

I believe in this concept, but the implementation described above is risky and invites failure. The problem is illustrated in Figure 4. The testing phase which occurs at the end of the development cycle is the first event for which timing, storage, input /output transfers, etc., are experienced as distinguished from analyzed. These phenomena are not precisely analyzable. They are not the solutions to the standard partial differential equations of mathematical physics for instance. Yet if these phenomena fail to satisfy the various external constraints, then invariably a major redesign is required. A simple octal patch or redo of some isolated code wil l not f ix these kinds of diff iculties. The required design changes are l ikely to be so disruptive that the software requirements upon which the design is based and which provides the rationale for everything are violated. Either the requirements must be modif ied, or a substantial change in the design is required. In effect the development process has returned to the origin and one can expect up to a lO0-percent overrun in schedule and/or costs.

One might note that there has been a skipping-over of the analysis and code phases. One cannot, of course, produce software wi thout these steps, but generally these phases are managed wi th relative ease and have l i tt le impact on requirements, design, and testing. In my experience there are whole departments consumed with the analysis of orbi t mechanics, spacecraft att i tude determination, mathematical opt imizat ion of payload activity and so forth, but when these departments have completed their di f f icul t and complex work, the resultant program steps involvea few lines of serial arithmetic code. If in the execution of their d i f f icul t and complex work the analysts have made a mistake, the correction is invariably implemented by a minor change in the code with no disruptive feedback into the other development bases.

However, I believe the illustrated approach to be fundamental ly sound. The remainder of this discussion presents five addit ional features that must be added to this basic approach to eliminate most of the development risks.

329

I SYSTE M

I ANALYSIS

PROGRAM DESIGN

I c o o , . o

TESTING

I OPERATIONS

Figure 2. Implementation steps to develop a large computer program for delivery to a customer.

I believe in this concept, but the implementation described above is risky and invites failure. The problem is illustrated in Figure 4. The testing phase which occurs at the end of the development cycle is the first event for which timing, storage, input /output transfers, etc., are experienced as distinguished from analyzed. These phenomena are not precisely analyzable. They are not the solutions to the standard partial differential equations of mathematical physics for instance. Yet if these phenomena fail to satisfy the various external constraints, then invariably a major redesign is required. A simple octal patch or redo of some isolated code wil l not f ix these kinds of diff iculties. The required design changes are l ikely to be so disruptive that the software requirements upon which the design is based and which provides the rationale for everything are violated. Either the requirements must be modif ied, or a substantial change in the design is required. In effect the development process has returned to the origin and one can expect up to a lO0-percent overrun in schedule and/or costs.

One might note that there has been a skipping-over of the analysis and code phases. One cannot, of course, produce software wi thout these steps, but generally these phases are managed wi th relative ease and have l i tt le impact on requirements, design, and testing. In my experience there are whole departments consumed with the analysis of orbi t mechanics, spacecraft att i tude determination, mathematical opt imizat ion of payload activity and so forth, but when these departments have completed their di f f icul t and complex work, the resultant program steps involvea few lines of serial arithmetic code. If in the execution of their d i f f icul t and complex work the analysts have made a mistake, the correction is invariably implemented by a minor change in the code with no disruptive feedback into the other development bases.

However, I believe the illustrated approach to be fundamental ly sound. The remainder of this discussion presents five addit ional features that must be added to this basic approach to eliminate most of the development risks.

329

I SYSTE M

I ANALYSIS

PROGRAM DESIGN

I c o o , . o

TESTING

I OPERATIONS

Figure 2. Implementation steps to develop a large computer program for delivery to a customer.

I believe in this concept, but the implementation described above is risky and invites failure. The problem is illustrated in Figure 4. The testing phase which occurs at the end of the development cycle is the first event for which timing, storage, input /output transfers, etc., are experienced as distinguished from analyzed. These phenomena are not precisely analyzable. They are not the solutions to the standard partial differential equations of mathematical physics for instance. Yet if these phenomena fail to satisfy the various external constraints, then invariably a major redesign is required. A simple octal patch or redo of some isolated code wil l not f ix these kinds of diff iculties. The required design changes are l ikely to be so disruptive that the software requirements upon which the design is based and which provides the rationale for everything are violated. Either the requirements must be modif ied, or a substantial change in the design is required. In effect the development process has returned to the origin and one can expect up to a lO0-percent overrun in schedule and/or costs.

One might note that there has been a skipping-over of the analysis and code phases. One cannot, of course, produce software wi thout these steps, but generally these phases are managed wi th relative ease and have l i tt le impact on requirements, design, and testing. In my experience there are whole departments consumed with the analysis of orbi t mechanics, spacecraft att i tude determination, mathematical opt imizat ion of payload activity and so forth, but when these departments have completed their di f f icul t and complex work, the resultant program steps involvea few lines of serial arithmetic code. If in the execution of their d i f f icul t and complex work the analysts have made a mistake, the correction is invariably implemented by a minor change in the code with no disruptive feedback into the other development bases.

However, I believe the illustrated approach to be fundamental ly sound. The remainder of this discussion presents five addit ional features that must be added to this basic approach to eliminate most of the development risks.

329

I SYSTE M

I ANALYSIS

PROGRAM DESIGN

I c o o , . o

TESTING

I OPERATIONS

Figure 2. Implementation steps to develop a large computer program for delivery to a customer.

I believe in this concept, but the implementation described above is risky and invites failure. The problem is illustrated in Figure 4. The testing phase which occurs at the end of the development cycle is the first event for which timing, storage, input /output transfers, etc., are experienced as distinguished from analyzed. These phenomena are not precisely analyzable. They are not the solutions to the standard partial differential equations of mathematical physics for instance. Yet if these phenomena fail to satisfy the various external constraints, then invariably a major redesign is required. A simple octal patch or redo of some isolated code wil l not f ix these kinds of diff iculties. The required design changes are l ikely to be so disruptive that the software requirements upon which the design is based and which provides the rationale for everything are violated. Either the requirements must be modif ied, or a substantial change in the design is required. In effect the development process has returned to the origin and one can expect up to a lO0-percent overrun in schedule and/or costs.

One might note that there has been a skipping-over of the analysis and code phases. One cannot, of course, produce software wi thout these steps, but generally these phases are managed wi th relative ease and have l i tt le impact on requirements, design, and testing. In my experience there are whole departments consumed with the analysis of orbi t mechanics, spacecraft att i tude determination, mathematical opt imizat ion of payload activity and so forth, but when these departments have completed their di f f icul t and complex work, the resultant program steps involvea few lines of serial arithmetic code. If in the execution of their d i f f icul t and complex work the analysts have made a mistake, the correction is invariably implemented by a minor change in the code with no disruptive feedback into the other development bases.

However, I believe the illustrated approach to be fundamental ly sound. The remainder of this discussion presents five addit ional features that must be added to this basic approach to eliminate most of the development risks.

329

I SYSTE M

I ANALYSIS

PROGRAM DESIGN

I c o o , . o

TESTING

I OPERATIONS

Figure 2. Implementation steps to develop a large computer program for delivery to a customer.

I believe in this concept, but the implementation described above is risky and invites failure. The problem is illustrated in Figure 4. The testing phase which occurs at the end of the development cycle is the first event for which timing, storage, input /output transfers, etc., are experienced as distinguished from analyzed. These phenomena are not precisely analyzable. They are not the solutions to the standard partial differential equations of mathematical physics for instance. Yet if these phenomena fail to satisfy the various external constraints, then invariably a major redesign is required. A simple octal patch or redo of some isolated code wil l not f ix these kinds of diff iculties. The required design changes are l ikely to be so disruptive that the software requirements upon which the design is based and which provides the rationale for everything are violated. Either the requirements must be modif ied, or a substantial change in the design is required. In effect the development process has returned to the origin and one can expect up to a lO0-percent overrun in schedule and/or costs.

One might note that there has been a skipping-over of the analysis and code phases. One cannot, of course, produce software wi thout these steps, but generally these phases are managed wi th relative ease and have l i tt le impact on requirements, design, and testing. In my experience there are whole departments consumed with the analysis of orbi t mechanics, spacecraft att i tude determination, mathematical opt imizat ion of payload activity and so forth, but when these departments have completed their di f f icul t and complex work, the resultant program steps involvea few lines of serial arithmetic code. If in the execution of their d i f f icul t and complex work the analysts have made a mistake, the correction is invariably implemented by a minor change in the code with no disruptive feedback into the other development bases.

However, I believe the illustrated approach to be fundamental ly sound. The remainder of this discussion presents five addit ional features that must be added to this basic approach to eliminate most of the development risks.

329

I SYSTE M

I ANALYSIS

PROGRAM DESIGN

I c o o , . o

TESTING

I OPERATIONS

Figure 2. Implementation steps to develop a large computer program for delivery to a customer.

I believe in this concept, but the implementation described above is risky and invites failure. The problem is illustrated in Figure 4. The testing phase which occurs at the end of the development cycle is the first event for which timing, storage, input /output transfers, etc., are experienced as distinguished from analyzed. These phenomena are not precisely analyzable. They are not the solutions to the standard partial differential equations of mathematical physics for instance. Yet if these phenomena fail to satisfy the various external constraints, then invariably a major redesign is required. A simple octal patch or redo of some isolated code wil l not f ix these kinds of diff iculties. The required design changes are l ikely to be so disruptive that the software requirements upon which the design is based and which provides the rationale for everything are violated. Either the requirements must be modif ied, or a substantial change in the design is required. In effect the development process has returned to the origin and one can expect up to a lO0-percent overrun in schedule and/or costs.

One might note that there has been a skipping-over of the analysis and code phases. One cannot, of course, produce software wi thout these steps, but generally these phases are managed wi th relative ease and have l i tt le impact on requirements, design, and testing. In my experience there are whole departments consumed with the analysis of orbi t mechanics, spacecraft att i tude determination, mathematical opt imizat ion of payload activity and so forth, but when these departments have completed their di f f icul t and complex work, the resultant program steps involvea few lines of serial arithmetic code. If in the execution of their d i f f icul t and complex work the analysts have made a mistake, the correction is invariably implemented by a minor change in the code with no disruptive feedback into the other development bases.

However, I believe the illustrated approach to be fundamental ly sound. The remainder of this discussion presents five addit ional features that must be added to this basic approach to eliminate most of the development risks.

329

Sprint n

realidade #2

ProblemasProblemas

Problemas

Problemas

Problemas

Problemas

Problemas

ProblemasProblemas

Problemas

Problemas

Problemas

Problemas

Problemas Problemas

Problemas

Projeto

=D

lidando com mudançasna realidade #1

• é rápido e indolor

• re-priorizar o backlog (lista de features)

• reunião de sprint planning

• resolve-se tudo em apenas uma reunião

realidade #1

Custo de mudançaC

usto

da

Mud

ança

Tempo

realidade #2

realidade #2 (metodologias ágeis)

realidade #1

entregasna realidade #2

25%

% prontorealidade #2

Projeto

Uso

2 meses de projeto

~25%

Entrega de Valor

Tempo

Valo

r E

ntre

gue

realidade #2

realidade #2 (metodologias ágeis)

realidade #1

faz sentido?

Fonte: Standish Group, CHAOS Report

16%!

27%!26%!

28%!

34%!

29%!

35%!

32%!

37%!

1994! 1996! 1998! 2000! 2002! 2004! 2006! 2008! 2011!

Evolução da Taxa de Sucessoem Projetos de Software

Metodologias Ágeis

Qual é melhor?

Lean Scrum XPvs. vs.

Lean - origens

• resposta da Toyota para sua crise, 1950

• precisava de “cash” no caixa (reduzir o inventário)

• reduzir custos

• melhorar qualidade

Lean

• Pull vs. Push Systems

• Kanban

• Pensamento Sistêmico

• Fluxo Equilibrado

• Células de Trabalho

• Melhoria Contínua

Scrum!"#$%&'()*+,"(

-&"%.(/01',"(

23%45,(

!"#$%&'()*&+,#-( ./"01'()*&+,#-(

.01&"#102*34#($#(567( 809'*(/*"*(

:7,;#"0*9(

<7,7*97(!,*1101-( ./"01'(!,*1101-( =*0,>(?9@( =76#( <7'"#9/7&5A*(

.#BC*"7(D%1&0#1*,(

Scrum

XP

• Test Driven Development

• Integração Contínua

• Entendimento Comum

• Pair-programming

• Ritmo sustentável

Qual é melhor?

Lean Scrum XPvs. vs.

É melhor!

Lean Scrum XP+ +

Lean + Scrum + XP

Tradicional Agileplanejar para antecipar “todos” os problemas

detectar problemase remover impedimentos

decisões são tomadaso quanto antes

decisões são adidaso máximo possível

passagem de bastãoentre especialistas

equipe unificadae multi-disciplinar

the big release(feedback tarde)

entregas contínuas(feedback contínuo)

perde-se tempo comnegociação com o cliente

gera-se valor comcolaboração com o cliente

obedecer o processo para controlar custos

ajustar o processo para otimizar a entregar de valor

seguir um plano responder à mudanças

vs.

Quem usa Agile?

2000 2001 2002 2003 2004 2005 2006 2007

Features Delivered per Team

Days between Major Releases

Transformation Results

+94 Increase in feature requests delivered -

2007 v. 2006

%

+38 Increase in feature requests delivered per

developer - 2007 v. 2006

%

Agile has delivered total visibility, total transparency and unbelievable productivity! a complete win! ”

Steve Fisher Sr. Vice President, Platform Product

Management Salesforce.com

568% more value

delivered in the first year

of being agile.

fonte: Greene and Fry 2008.