Portfólio 01 - Preços e Custos

3
............................................................................................................................... FORMACAO DE PRECOS E CUSTOS TECNOLOGIA EM GESTÁO FINANCEIRA – MODULO ESPECIFICO SIMONE CORREA FELIPE – RA 243222014 PORTFÓLIO 01 ............................................................................................................................... Guarulhos 2014

description

Trabalho para apresentação dos alunos de Mecatrônica da faculdade Eniac.

Transcript of Portfólio 01 - Preços e Custos

Page 1: Portfólio 01 - Preços e Custos

...............................................................................................................................

FORMACAO DE PRECOS E CUSTOS TECNOLOGIA EM GESTÁO FINANCEIRA – MODULO ESPECIFICO

SIMONE CORREA FELIPE – RA 243222014

PORTFÓLIO 01

...............................................................................................................................

Guarulhos 2014

Page 2: Portfólio 01 - Preços e Custos

SIMONE CORREA FELIPE

PORTFÓLIO 01

Trabalho apresentado ao Curso Tecnologia em Gestao Financeira da Faculdade ENIAC para a disciplina Formacao de Precos e Custos Prof. Ricardo Camargo de Araujo

...............................................................................................................................

Guarulhos 2014

Page 3: Portfólio 01 - Preços e Custos

AIVIDADE PROPOSTA

ITENS   VALOR  CUSTO  DIRETO  

CUSTO  INDIRETO   DESPESA  

EMBALAGEM   $60,000.00   $60,000.00          MAO  DE  OBRA  INDIRETA   $20,000.00       $20,000.00      SALARIOS  DE  VENDEDORES   $35,000.00           $35,000.00  MATERIAL  DE  SEGURANCA  -­‐  FABRICA   $12,000.00       $12,000.00      COMISSAO  DE  VENDAS   $32,000.00           $32,000.00  MAO  DE  OBRA  DIRETA   $80,000.00   $80,000.00          MATERIAL  DE  ESCRITORIO  -­‐  ADM   $9,000.00       $9,000.00      UNIFORMES  -­‐  FABRICA   $20,000.00       $20,000.00      IMPOSTO  PREDIAL  -­‐  ADM   $6,000.00           $6,000.00  SALARIOS  SUPERVISORES  -­‐  FABRICA   $25,000.00       $25,000.00      MATERIA  PRIMA   $115,000.00   $115,000.00          JUROS  PASSIVOS   $4,000.00           $4,000.00  COMPONENTES   $38,000.00   $38,000.00          SALARIOS  DA  ADMINISTRACAO   $22,000.00           $22,000.00  PROPAGANDA   $8,000.00   $8,000.00          AGUA  -­‐  FABRICA   $1,000.00       $1,000.00      ENERGIA  ELETRICA  -­‐  FABRICA   $10,000.00       $10,000.00      DESCONTOS  CONCEDIDOS   $3,000.00   $3,000.00          ALUGUEL  -­‐  FABRICA   $10,000.00       $10,000.00      TOTAL   $510,000.00   $304,000.00   $107,000.00   $99,000.00  

         COMPOSICAO  DE  CUSTO  DE  FABRICACAO  

                   MATERIA  PRIMA   $115,000.00  

       

COMPONENTES   $38,000.00      

   EMBALAGEM   $60,000.00  

       

M.O.  DIRETA   $80,000.00      

   (=)  CUSTO  DIRETO   $304,000.00  

       

(+)  CUSTOS  INDIRETOS   $107,000.00      

   (=)  CUSTO  FABRICACAO  TOTAL   $411,000.00  

       

VOLUME  PRODUZIDO   $50,000.00      

   CUSTO  DE  FABRICACAO  UNITARIO   $8.22