    TECHNICAL SECRETARIAT OF SEA

    PROCESS CODE:

    OBJECT OF THE CONTRACT:

    TERMS OF REFERENCE FOR CONTRACTING OF

    SUPERVISION OF ACQUISITION AND PROCESSING OF 2D

    MULTI-CHANNEL SEISMIC REFLECTION DATA

    Manta, October 2014

  • 8/10/2019 Tdrs Supervision (en)

    3/14

  • 8/10/2019 Tdrs Supervision (en)

    4/14

    Di reccin: Va Manta a San Mateo Km 5, a lado del Hotel Barbasquil lo, Edi f ici o Secretara Tcnica del MarTelfono: (593 5) 267 900 www.secretar iamar .gob.ec Correo-e: inf o@secretar iamar .gob.ecManta Ecuador

    4

    10.1 FORM OF PAYMENT Error! Marcador no definido.

    10.2 REFERENTIAL BUDGET Error! Marcador no definido.

    11 PLANNING ERROR! MARCADOR NO DEFINIDO.

    11.1 WORK BREAKDOWN STRUCTURE Error! Marcador no definido.

    11.2 PERIODIC REPORTS Error! Marcador no definido.

    12 BID ASSESMENT ERROR! MARCADOR NO DEFINIDO.

    13 CONTRACTING PROCESS AND CONSULTANCY MANAGEMENTERROR! MARCADOR NO

    DEFINIDO.

    14 ACRONYMS ERROR! MARCADOR NO DEFINIDO.

    15 ANNEXES ERROR! MARCADOR NO DEFINIDO.

  • 8/10/2019 Tdrs Supervision (en)

    5/14

    Di reccin: Va Manta a San Mateo Km 5, a lado del Hotel Barbasquil lo, Edi f ici o Secretara Tcnica del MarTelfono: (593 5) 267 900 www.secretar iamar .gob.ec Correo-e: inf o@secretar iamar .gob.ecManta Ecuador

    5

    TERMS OF REFERENCE FOR CONTRACTING OF SUPERVISION OF

    ACQUISITION AND PROCESSING OF 2D MULTI-CHANNEL SEISMIC

    REFLECTION DATA

    3 SUPERVISION OF ACQUISITION AND PROCESSING DATA ACTIVITIES FOR SETEMAR

    3.1 General ObjectiveThe overall objective is to monitor the process of acquisition and seismic processing, and acting as

    a representative and support of SETEMAR tasks in field and office; verify and certify the quality of

    information acquired in the field and office; and train technical personnel designated by SETEMAR

    in managing software packages that enable the processing of collected seismic data.

    3.2 Specific Objectives

    For this consultancy the following objectives are established:

    1. Develop the necessary steps to determine the acoustic transmission signal and applicableright reception to our geological and physical reality by calibrating the theoretical model of

    crane system with a practical model of data acquisition needed to ensure the quality of

    seismic data minimizing signal degradation due to factors that can be corrected prior to

    survey.

    2. Monitor the operations of collecting information on cruises Carnegie and Cocos, which daily

    reports shall be prepared during the acquisition phase ensuring proper quality control and

    quality assurance (QC / QA).

    3. Confirm the certification of personnel and equipment required for the proper performance of

    the work required by the SETEMAR.

    4. Confirm the deliverables in each one of the research and data collection to verify the qualityand accuracy of information.

    Figure 4. supervision and execution concept

  • 8/10/2019 Tdrs Supervision (en)

    6/14

    Di reccin: Va Manta a San Mateo Km 5, a lado del Hotel Barbasquil lo, Edi f ici o Secretara Tcnica del MarTelfono: (593 5) 267 900 www.secretar iamar .gob.ec Correo-e: inf o@secretar iamar .gob.ecManta Ecuador

    6

    ACQUISITION AND PROCESSING

    PLANNING

    TRANSIT

    DATA ACQUISITION

    ON-BOARD PROCESSING

    PROCESSING

    DELIVERY

    SUPERVISION

    PLANNING

    TRANSIT

    SUPERVISION OF ACQUISITION

    PROCESSING SUPERVISION

    PSDM PROCESSINGSUPERVISION

    TRAININGDELIVERABLESPREPARATION

    MONITOR

    Figure 4 illustrates the execution and supervision concept as a simultaneously activity for

    acquisition of 2D multichannel seismic data. The scope of supervision is restricted to acquisition

    and on-board PSTM processing of acquired data.

    4 SERVICE SCOPE OF SUPERVISION OF 2D MULTICHANNEL SEISMIC

    A company that has executed 2D multichannel seismic projects with extensive experience in project

    execution on the seabed data acquisition is required.

    The company must provide with technical personnel in geology and marine geophysics areas. All

    these personnel must have certified experience and studies of master degree to perform the

    assigned work. In general terms the supervision must meet the provisions of sections 6, 8 and 9 of

    the publication CLCS / 11, included in Annex B to the publication for consultation under section 9 inits Scientific Guidelines.

    During the acquisition process and seismic processing is necessary the staff training assigned by

    the Technical Secretariat of the Sea.

    4.1 DEFINITION AND SCOPE

    The servicing scope to "MONITOR" in these terms of reference includes the activities listed below:

    1. Platform and equipment supervision, sailing from the port of departure to the area of

    operation.2. Participation in campaigns for data collecting on the Cocos and Carnegie ridges and

    completion of activities at the end of campaigns.

    3. Supervision of the activities of data collection employed in the 2D multichannel seismic

    service. (Annex A contains the complete TDR of contracting service).

    4. Review and validation of the final report and submitted data by the company in charge of

    the seismic survey.

  • 8/10/2019 Tdrs Supervision (en)

    7/14

    Di reccin: Va Manta a San Mateo Km 5, a lado del Hotel Barbasquil lo, Edi f ici o Secretara Tcnica del MarTelfono: (593 5) 267 900 www.secretar iamar .gob.ec Correo-e: inf o@secretar iamar .gob.ecManta Ecuador

    7

    5 WORK METHODOLOGY

    The monitoring work is planned as a joint effort between supervision staff and technical personnel

    designated by SETEMAR. The purpose of supervision, further controlling the activities that are

    executed according to plan and planned methodology, is to ensure that the quality plan is fulfilled

    and develop future capabilities in planning and monitoring of multichannel seismic projects by

    meeting the following key activities:

    1. Ensure the seismic data quality.

    2. Verify the type of guns on the practical and conceptual level.

    3. Advise and prepare the reports required by the contract administrator for the proper

    performance of the acquisition consulting and seismic processing.4. Perform the compliance report of priori and posteriori tests related to obtain geological

    speed profile for further interpretation..

    5. Prepare the validation of reports and documents supporting for the receipt of deliverables

    by the contract manager.

    The execution shall be according to the next detail, in which the monitoring responsibilities related

    to working deadlines of processing and acquisition data, regarding with Figure 4 consist of the

    following tasks:

    During planning, vessel preparation and navigation in transit to Base Port, monitor the

    planning verifying the industry compliances determine the final stage of survey research to

    fulfill the tasks of acquisition and processing data stipulated by Setemar.

    During the acquisition cruise, the supervision will assign the qualified personnel who will

    perform as representatives of Setemar in the seismic survey, control the daily reports and

    data quality. Additionally a basic course plan for staff will be carried out by SETEMAR,

    which is assigned to the survey to perform quality control and management, analysis and

    data processing.

    To ensure the quality of seismic data, monitoring will validate before survey to verify the

    theoretical model of the gun system versus the practical acquisition model and determine

    the correct transmission acoustic signal and reception system to use tests and submit thereport on compliance with the following tests:

    a) DCO/Noise/Range Test

    b) RMS Noise Test, Channel-Gain Accuracy Test,

    c) Harmonic-Distortion Test, Common-Mode Rejection,

    d) Impulse-Response Test, Crosstalk Isolation Test,

  • 8/10/2019 Tdrs Supervision (en)

    8/14

    Di reccin: Va Manta a San Mateo Km 5, a lado del Hotel Barbasquil lo, Edi f ici o Secretara Tcnica del MarTelfono: (593 5) 267 900 www.secretar iamar .gob.ec Correo-e: inf o@secretar iamar .gob.ecManta Ecuador

    8

    e) Hydrophone Leakage Test.

    Validate the velocity model (RMS) low spatial density (coarse velocity model), with which it has

    become the (normal move out correction) NMO for a stack (geological cut) in which apreliminary interpretation will be made and will determine the level of processing required, thus

    the quality of the data that will enter the processing stage is checked. This model must be

    delivered at the end of acquisition phase by the responsible company for the 2D multichannel

    seismic. .

    At the end of the contract, the supervision is responsible for verifying that deliverables are

    required in the TDR and specified in the technical proposal, and is prepared in accordance

    with the scientific and technical guidelines in CLCS-11.

    6 INFORMATION AVAILABLE OF THE CONTRACTING PARTY

    The SETEMAR will make available to the Supervisory all the contractual information of Consultancy

    for data collection and processing of 2D multichannel seismic reflection.

    7 EXPECTED PRODUCTS OR SERVICES

    All products must strictly meet expected as indicated in the organic law of the national procurement

    system and its rules and likewise indicated in the CLCS / 11. The CONTRACTOR shall provide the

    following documents as a result of this consultation:

    1. Initial report of work in that the surveillance will indicate its working methods previously agreed

    with SETEMAR during technical meetings.

    2. The surveillance managing summarizes the following documents:

    a) Geometry report for seismic data acquisition and precision.

    b) Daily report of data acquisition.

    c) Report of compliance tests to determine the correct acoustic signal.

    d) Approval report of the low spatial density speed model.

    e) Report of seismic processing and appropriate methods for the procedures of seismic

    interpretation and of geological cuts. Weekly report that summarizes the performedactivities.

    f) Monthly report that includes a qualitative and quantitative assessment of project progress.

    g) Report on compliance with international standards applied to equipment, methods of

    acquisition and processing and staff education.

    3. Discrepancies and nonconformities registration that are in the execution of the acquisition and

    seismic processing and deliverables described in Annex A of TDR and specifications.

  • 8/10/2019 Tdrs Supervision (en)

    9/14

    Di reccin: Va Manta a San Mateo Km 5, a lado del Hotel Barbasquil lo, Edi f ici o Secretara Tcnica del MarTelfono: (593 5) 267 900 www.secretar iamar .gob.ec Correo-e: inf o@secretar iamar .gob.ecManta Ecuador

    9

    4. Verification reports of compliance with the various stages in the contract, which will be used as

    administrators support to issue the respective minutes of handover of all deliverables described in

    the consulting acquisition and processing of seismic data.

    5. Certification of each of the validations mentioned in the TOR and technical offer for the

    acquisition and data processing for SETEMAR.

    8 SCHEDULE FOR COMPLETION

    The total deadline of the consultancy, to deliver the processed information and Final Report in these

    terms of reference shall be one hundred eighty (180) calendar days from the signing of the contract

    and delivery of the advance payment. This deadline is divided as follows:

    Table 1. Contractual Deadline

    Consultancy Services Das Plazo

    Oversight of the preparation and transit of the vessel and priori test. 20

    Oversight of data collecting and processing at Carnegie and Cocos ridge, 60

    Oversight of the termination of the contract and receipt of deliverables.

    15

    TOTAL CONTRACTUAL TERM 95

    8.1 EXTENSION OF THE CONTRACT DEADLINE

    The Technical Secretariat of the Sea may extend the contract deadline only in the cases given

    below, with a prior request from the Contractor in a maximum of two days after the event arises, or

    when the facts show such need.

    a) Fortuity event or force majeure event, accepted by Setemar, in the terms established in the

    article 30, of the Civil Code.

    b) When the works or activities are suspended, considered in the schedule, change under

    Setemar disposition, and not due to circumstances attributable to the Contractor.

    c) Climatic or oceanographic conditions that prevent the normal development of the work.

    In case that the extension is accepted, Setemar will define its duration and incorporation of a new

    work schedule that will replace the original or previous schedule, which must be subscribed by the

    parties, and must have the same contractual value that the one replaced.

  • 8/10/2019 Tdrs Supervision (en)

    10/14

    Di reccin: Va Manta a San Mateo Km 5, a lado del Hotel Barbasquil lo, Edi f ici o Secretara Tcnica del MarTelfono: (593 5) 267 900 www.secretar iamar .gob.ec Correo-e: inf o@secretar iamar .gob.ecManta Ecuador

    10

    9 TECHNICAL STAFF, EQUIPMENT, RESOURCES

    Consistent with staff requirements for data acquisition, the consultant shall provide all personnel

    required, with the general and specific experience, according to detail in Table 6. The duties of

    these personnel will be held in jointly with the SETEMAR personnel designated to participate andmonitor the performance of the contract acquisition and data processing.

    Job title Area Education and experience

    Project Manager

    Acquisition and

    Processing

    Professional with Ph.D. in Geosciences with experience in

    project management of hydrographic and geophysical

    surveys. At least ten (10) years of experience in the area and

    not less than five (5) specific projects in that period.

    Supervisor ofGeology

    Acquisition

    Professional with Ph.D. in Geology Oceanography expert in

    paleo oceanography, paleo chemistry with experience and

    participation in projects of hydrographic and geophysicalsurveys. At least ten (10) years of experience as paleo paleo

    or chemical oceanographer and not less than five (5) specific

    projects in thatperiod.

    Supervisor of

    Geophysics:

    Seismic, GravityAcquisition

    Professional with Ph.D. in geology or geophysics experienced

    ten (10) years in studies of gravimetry and not less than five

    (5) projects gravimetry in the period.

    During the acquisition period at least one of the supervision technicians must be present

    permanently.

    10 PAYMENT TERMS AND CONDITIONS

    The payment term will be according item 13.1. After signing of the contract for the provision of the

    services required; an advance payment will be delivered and the difference will be paid according to

    item 13.1 and then the deliverable products are received to the entire satisfaction of Setemar, with

    the presentation of the approved invoice. For reception of the advance payment, the consultant

    shall submit a guarantee for the hundred (100%) percentage of the advance payment to receive.

    Upon completion of the service of the offeror, the Contract Administrator shall prepare a final report

    and signing of final acceptance delivery Act in accordance to what is stated in Article 124 of theGeneral Regulations of the Organic Law of the National System of Public Procurement.

    10.1 FORM OF PAYMENT

    The form of payment considered for the acquisition and processing of 2d multichannel seismic

    reflection data, according to SETEMARs requirements is the following:

  • 8/10/2019 Tdrs Supervision (en)

    11/14

    Di reccin: Va Manta a San Mateo Km 5, a lado del Hotel Barbasquil lo, Edi f ici o Secretara Tcnica del MarTelfono: (593 5) 267 900 www.secretar iamar .gob.ec Correo-e: inf o@secretar iamar .gob.ecManta Ecuador

    11

    Table 2. Form of payment for providing research platform

    Concept Total contract valuePercentage

    Initial report delivery 30 %

    Partial payments to be agreed according to the progress ofsupervision service.

    60 %

    At approval of the Final Report of the consultancy service and deliveryof all expected products.

    10%

    The price of the awarded bidder will be the price of the contract, unless otherwise agreed by the

    bidder and Setemar. The bidder must quote the prices in dollars of United States of America (USD).

    The SETEMAR reserves the right to pay in USD regardless of the currency in which it is quoted.

    Setemar will not refund any expense or rate not quoted in the proposal of the bidder. This includes

    accidental costs and transportation costs of the personnel or equipment.

    10.2 REFERENTIAL PAYMENT

    The total amount budgeted for this service is ----------- excluding value added tax (VAT) and other

    withholdings and taxes established by law.

    The activities and schedule breakdown are shown in Annex D.

    11 PLANNING

    11.1 WORK BREAKDOWN STRUCTURE

    Once the contract is subscribed, and in a period of (01) week, the Contractor shall prepare and

    submit for approval the Work Breakdown Structure (WBS) and its corresponding Gantt chart of the

    works to be carried out. This will be elaborated in a project management software designated by

    Setemar.

    The WBS is a hierarchical breakdown, based on the results of the works required to generate the

    deliverables,where each descending level of the WBS represents an increasing detailed definition

    of the works. The work planned is contained in the lowest level of WBS components, called work

    packages, which is a level that allows managing the progress of the work.

  • 8/10/2019 Tdrs Supervision (en)

    12/14

    Di reccin: Va Manta a San Mateo Km 5, a lado del Hotel Barbasquil lo, Edi f ici o Secretara Tcnica del MarTelfono: (593 5) 267 900 www.secretar iamar .gob.ec Correo-e: inf o@secretar iamar .gob.ecManta Ecuador

    12

    The WBS is prepared in the logical sequence of the project in a minimum of three (03) levels. The

    decomposition of the entire work into work packages involves the following activities:

    1. Identify and analyze the deliverables and the related work.

    2. Structure and organize the WBS3. Decompose the upper levels of the WBS into detailed lower levels.

    4. Develop and assign identification codes to the WBS components.

    5. Verify that the degree of work decomposition is the one necessary and is sufficient.

    11.2 PERIODIC REPORTS

    The Contractor shall submit a work plan for reports, based on the WBS, that allows keeping control

    of the daily, weekly and monthly progress of the works of the contract. The report formats, to be

    decided by the Contractor, should provide as minimum the following information:

    1. Daily progress based on activities planned.

    2. Planned cumulative weekly progress: Cumulative percentage of the planned progress for all

    works carried out in the week. Includes the breakdown and values by activity.

    3. Actual cumulative weekly progress: Percentage indicating the actual progress accumulated for

    all works carried out in the week. Includes comparison of planned and actual progress.

    4. Percentage of the cost of the activity: Total cost of the activity/Total cost of the project.

    5. Amount of the contract executed: Monetary value by activity, obtained by multiplying the unit

    cost by the actual progress.

    6. Executed monetary percentage of the activity: Amount of money executed/total cost of the

    project.

    7. Justification of delays in the fulfillment of the works planned.

    12 ASSESSMENT OF THE BID

    Tenders submitted in response to this TDR before the deadline will be assessed under the following

    criteria:

    1. Conditions of the scope of work.

    2. Technical specifications of the equipment.

    3. Experience in similar works.

    4. Job experience of the personnel assigned to the project.5. Timeframe of execution.

    6. Cost

    Setemar is not obliged to give any reason for the rejection of bids.

  • 8/10/2019 Tdrs Supervision (en)

    13/14

    Di reccin: Va Manta a San Mateo Km 5, a lado del Hotel Barbasquil lo, Edi f ici o Secretara Tcnica del MarTelfono: (593 5) 267 900 www.secretar iamar .gob.ec Correo-e: inf o@secretar iamar .gob.ecManta Ecuador

    13

    13 CONTRACTING PROCESS AND CONSULTANCY MANAGEMENT

    The contract of this project will be processed in accordance to the Organic Law of the Public

    Procurement National System and its General Regulations applicable to cases of this monetary

    value.

    The execution of this service does not involve an employment relationship between the parties.

    The Technical Secretariat of the Sea shall appoint a Contract Manager. However, at all stages of

    the process, there must be constant communication and coordination with the personnel designated

    by Setemar for the provision of information, validation and support in the process.

    14 ACRONYMS

    AMN : National Maritime Authority: Subsecretara de Puertos y TransporteMartimo y Fluvial

    CLCS : Commission on the Limits of the Continental Shelf

    CLCS/11 : Publication 11 of the Commission on the Limits of the Continental Shelf

    UNCLOS : United Nations Convention on the Law of the Sea

    DAOLS : The Division for Ocean Affairs and the Law of the Sea of the UN

    EIA : Environmental Impact Assessment

    FOS : Foot of the Slope

    BOS : Base of the Slope

    INOCAR : Oceanographic Institute of Navy (Instituto Oceanogrfico de la Armada)

    MAE : Ministry of Environment (Ministerio del Ambiente)

    MCS : Multi-channel seismic

    MTOP :Ministry of Transport and Public Works (Ministerio de Transporte y ObrasPblicas)

    UN : United Nations

    EMP : Environmental Management Plan

    PSTM : Pre Stack Time Migration

    PreSTM : Pre Stack Depth Migration

    PSDM : Post Stack Depth Migration

    SPTMF :Subsecretariat of Ports and Maritime and Fluvial Transportation(Subsecretara de Puertos y Transporte Martimo y Fluvial)

    SETEMAR : Technical Secretariat of the Sea (Secretaria Tcnica del Mar)

    STCW : Standards of Training, Certification and Watchkeeping

    EEZ : Exclusive Economic Zone

  • 8/10/2019 Tdrs Supervision (en)

    14/14

    Di reccin: Va Manta a San Mateo Km 5, a lado del Hotel Barbasquil lo, Edi f ici o Secretara Tcnica del MarTelfono: (593 5) 267 900 www.secretar iamar .gob.ec Correo-e: inf o@secretar iamar .gob.ecManta Ecuador

    14

    15 ANNEXES

    Annex A. Terms of reference for contracting of the acquisition and processing service of 2D

    multichannel seismic reflection data.

    Annex B. Publication CLCS / 11. Scientific and Technical Guidelines of the Commission on theLimits of the Continental Shelf, Approved by the committee on 13 May 1999

    Annex C. Proposal for 2D reflection MCS survey.