Annex 1 Appendix D - Sistema Interconectado Central

18
Annex 1 Appendix D Quality Assurance 2016 04 25 DRAFT Rev 15.docx 1 Santiago Solar LUMP SUM TURNKEY, ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT Contract No. _________ Annex 1 Appendix D Quality Assurance & Quality Control 25042016 Rev. 15

Transcript of Annex 1 Appendix D - Sistema Interconectado Central

Page 1: Annex 1 Appendix D - Sistema Interconectado Central

 

Annex 1 Appendix D Quality Assurance 2016 04 25 DRAFT Rev 15.docx   1 

Santiago Solar 

 

LUMP SUM TURNKEY, ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT 

 

Contract No. _________ 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Annex 1 Appendix D   

Quality Assurance & Quality Control 

   

   25‐04‐2016 

  Rev. 15 

 

   

Page 2: Annex 1 Appendix D - Sistema Interconectado Central

 

Annex 1 Technical Specification Appendix D 

QUALITY ASSURANCE & QUALITY CONTROL 

Content: 

1  General ........................................................................................................................................... 4 

2  QA / QC System and Organization ................................................................................................. 4 

2.1  QA/QC System ........................................................................................................................... 4 

2.2  QA/QC Manager ........................................................................................................................ 4 

2.3  Inspection and Test Plan (ITP) / Owners inspection rights ....................................................... 4 

2.4  Non‐Conforming Items .............................................................................................................. 5 

2.5  Independent Expert .................................................................................................................. 5 

2.5.1  Contractor’s Independent Expert (CIE) ............................................................................ 5 

2.5.2  Owner’s Independent Expert (OIE) .................................................................................. 5 

3  Quality Assurance during Construction and Commissioning ......................................................... 5 

3.1  Main Completion Certificates during Construction .................................................................. 5 

3.1.1  Tracks and Hardstands Complete ..................................................................................... 5 

3.1.2  Foundation Complete (per power plant subsystem / inverter segment) ........................ 6 

3.1.3  Mechanical Completion (per power plant subsystem / inverter segment) ..................... 6 

3.1.4  Electrical Completion (per power plant subsystem / inverter segment) ......................... 6 

3.1.5  Control System completion (per power plant subsystem / inverter segment) ............... 6 

3.1.6  Function test Completion (per power plant subsystem / inverter segment) .................. 6 

3.1.7  Commissioning Completion (per power plant subsystem / inverter segment) ............... 6 

3.1.8  Performance testing of power plant ................................................................................ 7 

3.1.9  Acceptance testing and complete facility performance testing ...................................... 7 

4  Inspection and Testing of Components ......................................................................................... 7 

4.1  Inverter & switchgear ................................................................................................................ 7 

4.2  MV/HV Transformer and HV electrical equipment ................................................................... 7 

4.3  PV Modules Testing ................................................................................................................... 7 

4.3.1  Objective ........................................................................................................................... 7 

4.3.2  Application area ............................................................................................................... 7 

4.3.3  Reference documents ...................................................................................................... 7 

4.3.4  Role and responsibility ..................................................................................................... 8 

4.3.5  Module power control procedure .................................................................................... 8 

 

 

Page 3: Annex 1 Appendix D - Sistema Interconectado Central

 

Annex 1 Technical Specification Appendix D 

QUALITY ASSURANCE & QUALITY CONTROL 

Abbreviations / Definitions 

AC  Alternating Current 

AM  Air Mass 

AME  Andes Mining Energy 

DC  Direct Current 

EL  Electroluminescence 

EPC  Engineering Procurement and Construction  (the contractual scheme) 

FNTP  Full Notice to Proceed 

HSE  Health, Safety and Environment 

HV  High Voltage 

HV‐TL  High Voltage Transmission Line 

IE  (Contractor’s or Owner’s) Independent Expert 

IEC  International Electrotechnical Convention 

ITL  Independent Test Laboratory 

ITP   Inspection and Test Plan 

I‐V (curve)  Current‐voltage curve 

(k)(M)Wh  Kilo or mega watt.hour 

LID  Light Induced Degradation 

LNTP  Limited Notice to Proceed 

LV, MV, HV  Low, Medium, High Voltage 

ML  Manufacturer Laboratory 

OE   Owners Engineer 

PID  Potential Induced Degeneration 

PV  Photovoltaic 

QA  Quality Assurance 

QC  Quality Control 

STC  Standard Testing Conditions  

Defined as: 1000W/m2 at 25°C module temperature, Air Mass AM1,5 

UV  Ultra‐violet 

VDE  Electrotechnical Association of Germany 

 

   

Page 4: Annex 1 Appendix D - Sistema Interconectado Central

 

Annex 1 Technical Specification Appendix D 

QUALITY ASSURANCE & QUALITY CONTROL 

1 GENERAL 

This document serves as Appendix D, part of “Annex 1 Technical Specification” to the EPC Contract and  therefore  constitutes  a  contractual  document.  It  describes  the QA/QC  requirements  for  the execution of the EPC Contract for the construction of a fully functional PV plant, including substation and transmission lines (“Project”). 

2 QA / QC SYSTEM AND ORGANIZATION 

2.1 QA/QC System 

Contractor  shall  implement a  state‐of‐the‐art QA/QC  system, where all equipment and works are controlled and tested and properly documented. Contractor shall enforce the QA/QC at his suppliers and subcontractors, and shall make the existence of such system a pre‐requisite for his procurement. 

The QA/QC System shall include, among other items, the following: 

‐ Quality Assurance (QA) program, ‐ Inspection &  Test  Plan  for manufactured  and  supplied materials.  This  shall  include  all major 

equipment such as for instance Modules, Inverters, Mounting Structures, HV and MV equipment, ‐ Quality Control (QC) and Inspection plan for construction and commissioning, ‐ Establishing and up‐to‐date keeping of all documentation at all phases of construction. 

2.2 QA/QC Manager 

Contractor shall appoint a designated QA/QC Manager  for  the complete Project duration, starting with Limited Notice To Proceed (LNTP) until final acceptance. The QA/QC‐Manager shall have more than 10 years of work experience and more than 5 years of experience in quality assurance and quality control for plants with similar complexity. Contractor shall present the QA/QC Manager to Owner for his approval. 

The QA/QC manager shall be responsible for all tasks related to the QA/QC of the project and shall be the counterpart for the Owners QA/QC representative. 

2.3 Inspection and Test Plan (ITP) / Owners inspection rights 

Contractor  shall prepare  a  comprehensive  Inspection‐  and  Test‐Plan  for  the  complete Project,  all subsystems, equipment and components. The ITP shall be submitted to owner after LNTP for approval. 

This shall include, but not be limited to the following: 

Workshop/Factory Inspection 

Owner has the right to inspect all manufacturing facilities and workshops for equipment related to the  Project.  EPC  Contractor’s QA/QC Manager  shall  arrange  all  access  and  visits with  respective Supplier/Subcontractor. Owner will give a 1 (one) week notice to Contractor for his intended visit. 

Witness inspection 

Owner reserves the right to attend and witness all relevant  inspection for equipment and material produced and procured for his project. Contractor shall provide a complete inspection plan at the start of the Project (with LNTP, to be updated with FNTP) for Owner’s review and comment. 

Contractor shall invite Owner with at least 2 weeks’ notice of any inspection event, even if dates as per original schedule are kept. 

Construction and Commissioning 

Page 5: Annex 1 Appendix D - Sistema Interconectado Central

 

Annex 1 Technical Specification Appendix D 

QUALITY ASSURANCE & QUALITY CONTROL 

Owner and his designated representatives shall have access to the complete construction site at all times.  Contractor  shall  provide  training  on  health,  safety  and  environment  (HSE)  regulations  as required. 

Documentation 

Contractor shall keep all files updated with a complete set  in his site office. Owner has the right to review and check documentation without prior notice. 

2.4 Non‐Conforming Items 

The Contractor must maintain a record of all non‐conforming items throughout the duration of the Project. This should reflect evidence of notification of the non‐conformance to the relevant party and the suggested course of action or an instruction issued to rectify the situation where necessary. 

The Contractor will provide the Employer’s Representative with copies of all non‐conformance notices issued throughout the duration of the Project. An updated register with evidence of close out of the non‐conformance where appropriate will be presented for review at the monthly progress meeting. 

2.5 Independent Expert 

2.5.1 Contractor’s Independent Expert (CIE) 

CIE  conducts  the necessary  tests and  inspections as  required by  the EPC Contract  (and described below) at his own costs. 

2.5.2 Owner’s Independent Expert (OIE) 

Owner shall have the right to select one or several OIE at his own expense to verify the work of the Contractor if he desires to do so. Contractor shall provide access to all tests, documentation etc to OIE or to Owner directly. 

The Owner will appoint a specific OIE within the frame of the Modules QC described below in 4.3. This Modules QC and the associated testing and inspection will be at Owner’s costs. 

3 QUALITY ASSURANCE DURING CONSTRUCTION AND COMMISSIONING 

Contractor shall prepare a detailed construction and commissioning plan and prepare checklists and certificates for each of the construction phases as listed below. 

Certificates shall be provided with original signatures from the supervisor responsible for the specific part of the work, from the Contractor’s QA/QC manager and Owner’s witnesses prior to hand‐over of system  to  next  construction  phase.  All  certificates  shall  be  kept  and  form  part  of  final  project documentation. 

All  certificates,  procedures  and  inspection  check‐lists  shall  be  prepared  by  the  Contractor  and submitted for approval to Owner prior to start of construction work. 

3.1 Main Completion Certificates during Construction 

3.1.1 Tracks and Hardstands Complete 

For each power plant segment, the Contractor shall prove that acceptable quality and CBR values are 

reached  in  order  to  ensure  proper  and  safe  traffic  and  stability. Based  on  the  technical  solution 

Page 6: Annex 1 Appendix D - Sistema Interconectado Central

 

Annex 1 Technical Specification Appendix D 

QUALITY ASSURANCE & QUALITY CONTROL 

selected and the materials used, the Contractor will carry out load bearing capacity tests with static 

plates and/or deflectometry tests (depending on the construction technique used).  

Minimum CBR shall be 10. 

At  least  one  test  per  500  linear meters  of  track  and  one  test  per  hardstand/crane  pad  shall  be 

performed. 

3.1.2 Foundation Complete (per power plant subsystem / inverter segment) 

For each power plant segment, prior to start of mechanical erection, the foundations shall be checked and  certified  to  be  in  accordance with  drawings  and  design  requirements  in  terms  of  location, alignment, quality of work and quality of provided materials (e.g.  samples of concrete shall be made and laboratory tested). 

3.1.3 Mechanical Completion (per power plant subsystem / inverter segment) 

For each power plant segment, mechanical completion shall be checked and certified prior to start of electrical works. Mechanical completion shall include the complete assembly of mounting structures and modules. Checks shall verify accordance with construction drawings and manuals, workmanship, alignment, no damages on materials, etc.  

3.1.4 Electrical Completion (per power plant subsystem / inverter segment) 

For each power plant segment, electrical completion shall be checked and certified prior to testing of systems. Checks  shall  verify  accordance with  construction drawings, proper  routing,  bending  and fixing of cables (UV protection, bending protection, etc.), certify the correct connection of each cable, testing of cable, labeling, etc. 

3.1.5 Control System completion (per power plant subsystem / inverter segment) 

For each power plant  segment,  completion of  control  system and all  connected  components and measurements  shall  be  checked  and  certified  prior  to  testing  of  systems.  Checks  shall  verify accordance with construction drawings, proper routing, bending and fixing of cables (UV protection, bending protection, etc.), certify the correct connection of each cable, testing of cable, labeling, etc. 

3.1.6 Function test Completion (per power plant subsystem / inverter segment)  

For each power plant segment, function tests shall be conducted according to a specific test plan to avoid any damage to equipments due to improper sequence or accidental operation. 

3.1.7 Commissioning Completion (per power plant subsystem / inverter segment)  

For  each  power  plant  segment,  commissioning  shall  be  conducted  according  to  a  specific commissioning  procedure  to  avoid  any  damage  to  equipments  due  to  improper  sequence  or accidental operation.  

The commissioning procedure shall be provided to the Owner for approval 3 Months prior to start of Commissioning activities. 

Page 7: Annex 1 Appendix D - Sistema Interconectado Central

 

Annex 1 Technical Specification Appendix D 

QUALITY ASSURANCE & QUALITY CONTROL 

3.1.8 Performance testing of power plant  

The completed system shall be performance tested based on specific performance test procedures, as may be provided within the EPC Contract or be approved by Owner prior to start of construction. Such performance  test will be a mandatory precondition  for  the Acceptance Test of  the complete power plant for Substantial Completion. 

3.1.9 Acceptance testing and complete facility performance testing 

Details are provided in the EPC Contract, Appendix A and Appendix D 

4 INSPECTION AND TESTING OF COMPONENTS 

4.1 Inverter & switchgear 

In addition to all standard QA procedures and good practices, thermographic measurements of all inverters  and  switch  gears  during  nominal  load  to  identify  processing  defects  or  improper connections. 

4.2 MV/HV Transformer and HV electrical equipment 

In  addition  to  all  standard  QA  procedures  and  good  practices,  all  sleeve  interconnections  and connections have to be documented with inspection sheets. 

 

4.3 PV Modules Testing 

The majority of the tests described in this section will be done in the power plant site (installed module 

or in onsite test  laboratory). The onsite Test Laboratory will be of recognized prestige and must be 

acceptable by all the involved parties: Owner, Contractor and PV Modules Manufacturer. 

Owner will execute samples when modules are delivered on site. In case samples show no compliance 

with the agreed module specification according to Annex 1 Technical Specification, owner will execute 

a  module  testing  process  as  described  below.  If  any  of  the  selected  parts  do  not  satisfy  the 

requirements as described in this document then contractor shall fulfill the condition as described in 

the clause “Testing of Sample Products” of the agreement.  

4.3.1 Objective 

The objective  is to define a QA procedure to evaluate the performance and quality of photovoltaic modules. 

4.3.2 Application area 

This process can be used to evaluate the nominal power and general quality of photovoltaic modules coming from approved or under approval suppliers of Owner. 

4.3.3 Reference documents  

Proposed tests are based on the following international standards: 

Page 8: Annex 1 Appendix D - Sistema Interconectado Central

 

Annex 1 Technical Specification Appendix D 

QUALITY ASSURANCE & QUALITY CONTROL 

‐ IEC 61215 Crystalline silicon terrestrial photovoltaic (PV) modules – Design qualification and type approval. 

‐ International Standards in testing of PV modules. 

The tests will be performed by Owner or Owner’s Representative / OIE and supervised by Contractor or Contractor’s Representative / CIE based on IEC 61215 standards. 

4.3.4 Role and responsibility 

The execution of the tests and inspections by the Owner. All test equipment must comply with latest applicable norms and standards considering industry practice for TIR1 supplier.  

- The Contractor (via Module Manufacturer) must provide: o The modules o The tolerance ranges o The module « Flash list » data  o The electroluminescence images 

 - Owner / OIE must: 

o Define the sampling method o Execute test as listed below o Provide a report on visual inspection of photovoltaic modules o Provide  results on measured  characteristics  current‐voltage  at  STC  conditions  for 

each module sample o Provide results on LID (Light Induced Degradation) for the sample o Provide results of Electroluminescence –EL images and defects classifications o Provide a detailed report on measurement results o Provide raw data of the done measurements. 

 

4.3.5 Module power control procedure 

4.3.5.1 Sampling method 

Module samples must be randomly selected from a lot or a sub batch of produced modules (included in a « flash list »). 

Sampling method should be agreed with the Contractor according with the International Standard ISO 2859. 

Sampled quantity is detailed in below as agreed by both Parties. The modules must be produced in the same conditions and using the same manufacturing process as usual. These modules must have undertaken first an inspection and a quality control as defined by the module manufacturer. 

The module  sampling  to  test must be  selected  according  to a  statistic method  in  function of  the nominal  power  at  STC  conditions,  the  manufacturing  date  and  the  confidence  level  of  the manufacturer. This  statistic method allows a  representative  sample  to be chosen  from  the whole production lot or sub‐batch. 

The percentages of modules to be tested will be based in the International Standard ISO 2859: 

- The  quantities  for  testing  and  accordingly  for  rejection  considers  a  Batch  Size  of  11440 Modules 

- Special Inspection Level according to below table - Acceptable Quality Level according to below table depending on the test 

Page 9: Annex 1 Appendix D - Sistema Interconectado Central

 

Annex 1 Technical Specification Appendix D 

QUALITY ASSURANCE & QUALITY CONTROL 

 

Visual Inspection. 

Modules Electrical Characteristics 

Images with Electroluminescence (EL) camera. 

EVA cross linking degree. 

Thermography 

UV resistance 32 

Peel Test 

Leakage test 

Potential Induced Degradation (PID)  In case of one or more of the previous type of tests fail, Elecnor reserves the right (at its cost) to retest with presence of OIE the PV modules. In case the test of Client is confirmed (number of failed modules above acceptable number of failed modules) the relevant batch / sub batch shall be rejected. Contractor might test with presence of OIE at his own costs sub batches considering a sample size  based  on  the  same  inspection  level  and based  on  the  same  quality  requirements  as defined below. In case number of failed modules in the retest are within the required quality level, these sub batches can be used for the power plant. The  test quantities  in  the  table below are defined  for one Batch of 11440 Modules  (or 20 container); in case one batch is divided in sub batches upon request of contractor, the number of tested modules to justify a rejection has to be adapted considering the norm ISO 2859 with the respective Inspection level as defined for each test in the below table. In case contractor is requesting such division in sub batches, the additional testing is at contractor costs.  

   

Page 10: Annex 1 Appendix D - Sistema Interconectado Central

 

Annex 1 Technical Specification Appendix D 

QUALITY ASSURANCE & QUALITY CONTROL 

10 

Table 1: Summary of Sample Selection and Fail Criteria for Module Testing 

Item Test Description

Inspection Level

Number of Modules for

each batch with approximately 11440 modules (20 container)

Acceptance Criteria Fail Consequence / Comment

4.3.5.2 Visual Inspection.

G-1 125

AQL = 1 for critical defects as defined below

Failed Module allowed = 3 AQL = 1 for major defects based

on IEC 61215 definition Failed Module allowed = 3

AQL = 2.5 for minor defects based on IEC 61215 definition

Failed Module allowed = 7

Fail: Rejection of Batch

4.3.5.3

Modules Electrical Characteristics: Power/I-V/LID

G-1 125 AQL = 2.5

Failed Module allowed = 7

Fail: Compensation of reduced output with additional installed capacity or Economical compensation if no additional power can be installed based on site restrictions or approval restrictions (please refer to detail below) or rejection of batch (Contractor decision)

4.3.5.4

Images with Electroluminescence (EL) camera.

G-1 125 AQL = 1.5

Failed Module allowed = 5

Fail: Reject of Batch

4.3.5.5 EVA crosslinking degree.

1 module for 2

batches No AQL Level

Failed Module allowed = 0

Destructive Testing Failed Module rejection of both batches Same Modules will be used both for EVA Cross Linking Test and Peel Test

4.3.5.6 Thermography 10% Failed modules to be replaced In case of failure additional measurements to be agreed between parties

4.3.5.8 Peel Test 1 module for 2

batches No AQL Level

Failed Module allowed = 0

Destructive Testing Failed Module rejection of both batches Same Modules will be used both for EVA Cross Linking Test and Peel Test

4.3.5.9 Leakage test

2 per batch but no less than 1

per MW in average

No AQL Level Failed Module allowed = 0

Fail: Reject of Batch

4.3.5.10

Potential Induced Degradation (PID)

2 per batch but no less than 1

per MW in average

No AQL Level Failed Module allowed = 0

Fail: Reject of Batch

  

4.3.5.2 Visual inspection 

i. Test description 

This test objective is to detect any visual defect on the modules. The Laboratory must inspect carefully all the modules of the sample with a light intensity superior or equal to 1 000 lux in order to check the following defects according to Supplier’s visual inspection criteria:  

Page 11: Annex 1 Appendix D - Sistema Interconectado Central

 

Annex 1 Technical Specification Appendix D 

QUALITY ASSURANCE & QUALITY CONTROL 

11 

‐ Cracked, bent, misaligned or torn external surfaces; ‐ Broken cells; ‐ Cracked cells; ‐ Faulty interconnections or joints; ‐ Cells touching one another or the frame; ‐ Failure of adhesive bonds; ‐ Bubbles or delamination forming a continuous path between a cell and the edge of the module; ‐ Tacky surfaces of plastic materials; ‐ Faulty terminations, exposed live electrical part; ‐ Any other conditions which may affect performance. 

Make note of and/or photograph the nature and position of any cracks, bubbles or delamination, etc. which may worsen and adversely affect the module performance in subsequent tests. 

 

 

ii. Acceptation criteria 

A module design and aspect shall be judged to have passed the visual qualification tests, if each test sample meets the following criteria: 

‐ No broken, no cracked and no torn external surfaces, including superstrates, substrates, frames and junction boxes; 

‐ Both of horizontal  and  vertical dislocation of  cell  strings  (maximum  exposure of  cell bus bar metallization) ≤ 2mm with offset length;  

‐ The junction box should be parallel to the backsheet or frame.  ‐ No  bent  and  no misaligned  external  surfaces,  including  superstrates,  substrates,  frames  and 

junction  boxes  to  the  extent  that  the  installation  and/or operation of  the module would be impaired. 

‐ No crack in a cell the propagation of which could remove more than 10% of that cell’s area from the electrical circuit of the module; 

‐ No bubbles and no delamination forming a continuous path between any part of the electrical circuit and the edge of the module; 

Loss of mechanical integrity, to the extent that the installation and/or operation of the module would be impaired.  

Test execution:       Test  to be done before  installation of module  in  the onsite         laboratory.  Time  between  arrivals  of  relevant  container  to        site to fail report maximum 20 calendar days 

 Quantity to be tested:  According to ISO 2859: Inspection Level G1 normal 

inspection. 

 AQL‐Level:        1 for all critical defects as listed above (3 failures allowed) 

          For additional major defects according to IEC 61215 AQL = 1 

          (3 failures allowed).For additional minor defects according to 

          IEC 61215 AQL = 2.5 (7 failures allowed) 

Page 12: Annex 1 Appendix D - Sistema Interconectado Central

 

Annex 1 Technical Specification Appendix D 

QUALITY ASSURANCE & QUALITY CONTROL 

12 

 

4.3.5.3 Modules electrical characteristic 

i. Test description 

The current‐voltage characteristic I‐(V) and the STC power from each module is determined according to the IEC standard IEC 61215. 

The test must be conducted with a class AAA sun simulator according to IEC 60904. 

The calibration must be traceable to SI‐standards. The reference device must have an uncertainty of <1% for Isc. 

The STC power is the power at Standard Test Conditions: 1000 W/m2, at 25°C  

The measurement uncertainty must be as low as possible but up to the agreed third party testing lab ability for silicon technology. A measurement of spectral response is done for one reference module. 

For each module, the laboratory will do 3 consecutive I‐V measurements. 

 

For C‐Si modules,  the Light‐Induced‐Degradation  (LID)  is measured on sampling modules with  the following conditions;  

‐ Exposure to 20kWh of natural sunlight  ‐ During exposure, modules are kept close to MPP.  Quantity to be tested:      According to ISO 2859 Inspection Level  G‐1   

ii. Acceptance criteria 

Each test samples need to meet the following criteria: 

1. The  module  individual  power  at  STC  should  be  in  the  positive  tolerance  range  and comparable to the Nominal Power agreed by both parties. 

2. The average STC‐power must be equal or above nameplate power. 3. All modules  I‐V curves have a smooth behavior according characteristics  in  the  range of 

values given by the manufacturer 4. LID measurement must be in the range of values given by the manufacturer 

 Quantity to be tested:   According to ISO 2859: Inspection Level G1 normal 

inspection 

AQL‐Level:        2.5 (applicable only for criteria 1, 3 and 4) 

Test criteria 2 average STC‐power must be equal or above nominal power of the module. If the 

average STC‐power is below the nominal power of the module the test failed 

Consequence in case of test failure 

In case of failure the measured values of the test are used as supporting values for a new simulation 

and the substandard performance is determined by way of calculation. In such case additional 

modules must be installed in order to satisfy the Power Guaranty, if possible pursuant to the 

applicable permits and space constraints. If additional modules can’t be implemented in the existing 

Page 13: Annex 1 Appendix D - Sistema Interconectado Central

 

Annex 1 Technical Specification Appendix D 

QUALITY ASSURANCE & QUALITY CONTROL 

13 

plant based on space and permit constraints, reduced installed capacity has to be compensated with 

a price reduction of the facility equivalent to Liquidated Damages for underperformance as defined 

in Appendix D of the contract. This means for each percent reduced installed capacity of the plant 

(and fractions of this), contractor will i) reduce the full turnkey EPC price 1.5 % or ii) increase 

guarantee PR in the same proportion.  

If contractor pays compensation for reduced installed capacity based on electrical testing, the 

reduced installed capacity shall be considered in the performance calculation according to Appendix 

D of the contract. In the same way, if contractor compensates the reduced installed capacity with an 

increase of PR, this new PR shall be considered in the performance calculation according to 

Appendix D of the contract. 

If criteria 2 average STC‐power if more than 2 % below nominal output of the Module the batch shall 

be rejected and replaced with new modules. 

 Test execution:   Test to be done before installation of module in the onsite        laboratory. Time between arrivals of relevant container to        site to fail report maximum 20 calendar days for all electrical        testing (except LID measurement). Time between for fail       report LID measurement as quick as possible. 

 

4.3.5.4 Images with Electroluminescence (EL) camera 

i. Test description 

The objective is to control the number and type of cell defects (micro‐cracks, broken fingers…). 

For each module, EL measurements are done in injecting current with the same value as module short circuit condition. 

For each module, the laboratory summarizes the following defects: 

‐ Estimated module defective active area  ‐ Maximum cell defective area ‐ Presence of cell defective area caused by crack ‐ Presence of cell with multiple cracks ‐ Number of cracks and micro‐cracks in module classified in the following categories 

Cross cracks  Perpendicular to busbars  Parallel to busbars  45° oriented  Dendritic cracks  Cracks with other directions 

‐ Presence of grid finger defects ‐ Presence of inactive cells ‐ Existing evident EL contrast among cell ‐ Presence of contact molding defect ‐ Presence of soldering defects ‐ Evidence of slope breakage in I(V) curve 

 Quantity to be tested:      According to ISO 2859 Inspection Level G‐1 

Page 14: Annex 1 Appendix D - Sistema Interconectado Central

 

Annex 1 Technical Specification Appendix D 

QUALITY ASSURANCE & QUALITY CONTROL 

14 

 

ii. Acceptance criteria 

The tested modules must comply with micro‐cracks specifications attached below: 

Page 15: Annex 1 Appendix D - Sistema Interconectado Central

 

Annex 1 Technical Specification Appendix D 

QUALITY ASSURANCE & QUALITY CONTROL 

15 

Table 2: Definition of fulfilment of micro‐cracks specification 

Page 16: Annex 1 Appendix D - Sistema Interconectado Central

 

Annex 1 Technical Specification Appendix D 

QUALITY ASSURANCE & QUALITY CONTROL 

16 

‐ AQL‐Level:       1.5 (failed modules allowed = 5 modules 

 Test execution:       Test  to be done before  installation of module  in  the onsite           laboratory.  Time  between  arrivals  of  relevant  container  to           site to fail report maximum 20 calendar days 

 

4.3.5.5 EVA crosslinking degree 

The determination of the EVA crosslinking degree gives an indication of the production quality (oven 

temperature, homogeneity, duration). A poor crosslinking degree has an adverse effect on the service 

life of the module. The data sheet  information of the EVA supplier is deemed as the pass criterion. 

The test method is wet‐chemical, i.e it is not an exact physical measuring method and afflicted with a 

high degree of uncertainty. This fact is taken into account in the pass criteria. 

 

Quantity to be tested:      1 module for 2 batches 

Test Characteristic      Destructive Testing 

Method of testing:      Soxleth extraction in Xylene. 

Pass Criteria:        Minimum 65% (measurement tolerance considered) 

If the module fails, both batches rejected 

Test execution:       Test  to be done before  installation of module  in  the onsite           laboratory.  Time  between  arrivals  of  relevant  container  to           site to fail report maximum 30 calendar days 

4.3.5.6 Thermography 

Quantity to be tested:      10 % 

Test / Pass Criteria: 

‐ Temperature difference between the substrings within a module is less than 5 K.  

‐ Temperature difference between single cells within a module is less than 10K.  

‐ Less than 5 cells within a module have a temperature deviation from average greater than 5 K . 

If not, then the performance deviation shall be less than 10% of the value in the SF flash report. 

Note: Adaptation of the limits after joint measurement onsite and, where appropriate, verification 

in the laboratory.  

Consequence: 

‐ Failing modules to be replaced; in case of significant number of failure increase of test quantity 

to be mutually agreed 

Page 17: Annex 1 Appendix D - Sistema Interconectado Central

 

Annex 1 Technical Specification Appendix D 

QUALITY ASSURANCE & QUALITY CONTROL 

17 

Test execution:       Test to be done after module installation on structure 

 

4.3.5.7 Peel test 

This test is used to check as to whether the EVA/backsheet adhesion complies with the manufacturer's 

specification. This measurement  is not possible  in all cases because  the backsheet may adhere so 

strongly that, instead of allowing for peeling off, it tends to tear inherently. 

Quantity to be tested:      1 module for 2 batches 

Test Characteristic      Destructive Testing 

Pass Criteria:        60 N/cm EVA vs glass, 20 N/cm for EVA backsheet   

If the module fails, both batches rejected 

Test execution:       Test  to be done before  installation of module  in  the onsite           laboratory.  Time  between  arrivals  of  relevant  container  to           site to fail report maximum 30 calendar days 

4.3.5.8 Leakage test 

Wet leakage test according to IEC 61215. Power is applied to the short‐circuited module in the water 

bath and the leakage current is measured. This test is used to determine the insulation resistance. It 

is a safety test. 

Quantity:        2 modules per batch but no less than 1 per MW in average. 

Test Criteria:         

Pass criteria        40 MOh/m² considering IEC 61215   

If the 1 module fails, the batch is rejected 

 Test execution:       Test  to be done before  installation of module  in  the onsite           laboratory. Time between arrivals of relevant container to site           to fail report maximum 20 calendar days  

4.3.5.1 Potential Induced Degradation (PID) 

The PID test shall identify the Potential‐Induced Degradation resulting from voltage influence on the 

module. It is a degradation resulting in lower output, which can occur on one side of a string. The test 

procedure  is  not  yet  standardized,  but  a  procedure  recommended  from  several  Module 

manufacturers. During the PID test, a negative potential of ‐1000V is induced between cell and module 

frame. The glass cover shall have contact with the frame via aluminum foil (IEC 62804 TS, Methode B). 

Before and after  the  test, EL measurements and STC output measurements will be carried out  to 

determine  the effect on  the modules. Additionally,  the  isolating  resistivity of  the modules will be 

measured after the test. 

Page 18: Annex 1 Appendix D - Sistema Interconectado Central

 

Annex 1 Technical Specification Appendix D 

QUALITY ASSURANCE & QUALITY CONTROL 

18 

 

Quantity:        2 modules per batch but no less than 1 per MW in average. 

Test Criteria:  STC measurement before and after exposure to bias. Max. 

Power loss < 5%. Exposure 168h at 25°C ‐1000V at inner 

circuit, front glass covered with grounded aluminum foil. 

If the 1 module fails, the batch is rejected 

Test execution:  Test to be done in the onsite laboratory. Time between 

arrivals of container on site to fail report to be minimized 

according to applicable test sequence.