MINISTÉRIO DO PLANEJAMENTO Public Private Partnerships Fiscal Issues in Brazil MINISTÉRIO DO...

20
MINISTÉRIO DO PLANEJAMENTO Public Private Partnerships Fiscal Issues in Brazil MINISTÉRIO DO PLANEJAMENTO Cuernavaca, Mx, 26/11/2008 Seminário de Intercâmbio Regional Aspectos Técnicos de los Proyectos para las Asociaciones Público-Privadas

Transcript of MINISTÉRIO DO PLANEJAMENTO Public Private Partnerships Fiscal Issues in Brazil MINISTÉRIO DO...

Page 1: MINISTÉRIO DO PLANEJAMENTO Public Private Partnerships Fiscal Issues in Brazil MINISTÉRIO DO PLANEJAMENTO Cuernavaca, Mx, 26/11/2008 Seminário de Intercâmbio.

MINISTÉRIO DO PLANEJAMENTO

Public Private Partnerships

Fiscal Issues in Brazil

MINISTÉRIO DO PLANEJAMENTO

Cuernavaca, Mx, 26/11/2008

Seminário de Intercâmbio RegionalAspectos Técnicos de los Proyectos para las

Asociaciones Público-Privadas

Page 2: MINISTÉRIO DO PLANEJAMENTO Public Private Partnerships Fiscal Issues in Brazil MINISTÉRIO DO PLANEJAMENTO Cuernavaca, Mx, 26/11/2008 Seminário de Intercâmbio.

MINISTÉRIO DO PLANEJAMENTOMINISTÉRIO DO PLANEJAMENTOASSESSORIA ECONÔMICA - ASSEC

Institutional Framework

Law 11.079

Projects

Page 3: MINISTÉRIO DO PLANEJAMENTO Public Private Partnerships Fiscal Issues in Brazil MINISTÉRIO DO PLANEJAMENTO Cuernavaca, Mx, 26/11/2008 Seminário de Intercâmbio.

MINISTÉRIO DO PLANEJAMENTOMINISTÉRIO DO PLANEJAMENTOASSESSORIA ECONÔMICA - ASSEC

PPPs on Brazilian Legal Framework

PPP

Law 11.079/0

4

Concessions

8.987/959.074/95

PPP

11.079/04

e

Law of Public Licitations

8.666/93

Sustainable projects

Traditional projects of public investments and public

procurement

Partially sustainable projects by means of

public resources

Inde

pend

ent R

even

ue

Gener

ation

Cap

acity

Page 4: MINISTÉRIO DO PLANEJAMENTO Public Private Partnerships Fiscal Issues in Brazil MINISTÉRIO DO PLANEJAMENTO Cuernavaca, Mx, 26/11/2008 Seminário de Intercâmbio.

MINISTÉRIO DO PLANEJAMENTOMINISTÉRIO DO PLANEJAMENTOASSESSORIA ECONÔMICA - ASSEC

PPP definition in Brazil

Concessão patrocinada (Sponsored Concession)

Common concession of public services Origin of revenue: tariff + public payments

Concessão administrativa (Administrative Concession)

Direct or indirect services to the Public Administration– Public services– Economic activities not listed as public services

Origin of revenue: public payments

Page 5: MINISTÉRIO DO PLANEJAMENTO Public Private Partnerships Fiscal Issues in Brazil MINISTÉRIO DO PLANEJAMENTO Cuernavaca, Mx, 26/11/2008 Seminário de Intercâmbio.

MINISTÉRIO DO PLANEJAMENTOMINISTÉRIO DO PLANEJAMENTOASSESSORIA ECONÔMICA - ASSEC

Who Is Involved in the Decision (Federal level)

CGP – PPP Council, composed of:Ministry of FinanceMinistry of Planning, Budget and Management;Ministry of Presidency

Fiscal controlsNational TreasuryTribunal de Contas da União (Federal Auditing Office)

ModellingMinistry that sponsors the project (budget)PPP task force of the Ministry of Planning, Budget and Finance

Page 6: MINISTÉRIO DO PLANEJAMENTO Public Private Partnerships Fiscal Issues in Brazil MINISTÉRIO DO PLANEJAMENTO Cuernavaca, Mx, 26/11/2008 Seminário de Intercâmbio.

MINISTÉRIO DO PLANEJAMENTOMINISTÉRIO DO PLANEJAMENTOASSESSORIA ECONÔMICA - ASSEC

Law 11.079

Institutional Framework

Projects

Page 7: MINISTÉRIO DO PLANEJAMENTO Public Private Partnerships Fiscal Issues in Brazil MINISTÉRIO DO PLANEJAMENTO Cuernavaca, Mx, 26/11/2008 Seminário de Intercâmbio.

MINISTÉRIO DO PLANEJAMENTOMINISTÉRIO DO PLANEJAMENTOASSESSORIA ECONÔMICA - ASSEC

Project development, construction, financing, operation by the private sector and transfer of assets, at the end of the contract, to the public sector;

Law is valid for the Public Administration, public foundations, special public funds, state owned enterprises and other entities controled directly or indirectly by federal, state or municipal governments;

Minimum amount: R$ 20 million (around US$ 9,1 million);

Contract duration: between 5 and 35 years;

The object of the contract can´t be solely hiring people, equipament acquisition or construction of facilities;

Public payments conditioned on the availability of the service;

Although the law subsidises itself in many points in the Concession Law, they don´t co-habitate in the bidding process.

PPP’s Law Main Caracteristics

Page 8: MINISTÉRIO DO PLANEJAMENTO Public Private Partnerships Fiscal Issues in Brazil MINISTÉRIO DO PLANEJAMENTO Cuernavaca, Mx, 26/11/2008 Seminário de Intercâmbio.

MINISTÉRIO DO PLANEJAMENTOMINISTÉRIO DO PLANEJAMENTOASSESSORIA ECONÔMICA - ASSEC

PPP’s Law Main Caracteristics (cont.) Resources from public payments come from the budget of the ministry

directly involved, or from the budget of the independent state owned enterprise (it´s not “added”);

Public payments cannot be delayed (is immune to the National Treasury´s “scissor”);

Main fiscal control at the federal level: Limit of 1% of previous annual “current liquid revenue*” with public payments of

PPPs, for the federal government (more or less R$ 4,0 billion in 2008 – US$ 1,82 billion);

Sponsored concessions where more than 70% of revenues comes from public payments depends on authorization from the Congress.

Step-in Rights

* Revenue from taxes, government financial assets and dividends from state owned companies less compulsory transfers and pensions.

Page 9: MINISTÉRIO DO PLANEJAMENTO Public Private Partnerships Fiscal Issues in Brazil MINISTÉRIO DO PLANEJAMENTO Cuernavaca, Mx, 26/11/2008 Seminário de Intercâmbio.

MINISTÉRIO DO PLANEJAMENTOMINISTÉRIO DO PLANEJAMENTOASSESSORIA ECONÔMICA - ASSEC

Public payments garanteed by the PPPs Fund of Garantees (FGP);

FGP – Fundo Garantidor de PPPs

Begins in feb/2006 with assets of R$ 3,15 billion (= US$ 1,43 billion) in stocks (Petrobrás, Vale, Banco do Brasil, etc);

Rules don´t allow leveraging of obligations (the ration between abligations and assets must be equal or less than 1);

Allows garantees to be constituted under various juridical instruments; Fund is operated by Banco do Brasil, not the government;

As garantees can also be used bank garantees, insurance, public revenue segregation, garantees from multilateral institutions, etc.

PPP’s Law Main Caracteristics (cont.)

Page 10: MINISTÉRIO DO PLANEJAMENTO Public Private Partnerships Fiscal Issues in Brazil MINISTÉRIO DO PLANEJAMENTO Cuernavaca, Mx, 26/11/2008 Seminário de Intercâmbio.

MINISTÉRIO DO PLANEJAMENTO

Estimation of future obligations for the next 10 years;

The estimations must be accomodated in the government budgetary law (looking ahead 4 years);

The rules regarding the consolidation of PPP’s financial compromises as public debt were stated by the National Treasury;

The rule states that if a contract of PPP incur in risk of demand or construction or availability, it must be treated as debt;

That’s not a problem for the Federal Government, but some states and municipalities don’t have margin for new debt assumptions;

SOE are part of the 1% limit, even if they have an independent budget.

Compliance with Fiscal Responsability Law

Page 11: MINISTÉRIO DO PLANEJAMENTO Public Private Partnerships Fiscal Issues in Brazil MINISTÉRIO DO PLANEJAMENTO Cuernavaca, Mx, 26/11/2008 Seminário de Intercâmbio.

MINISTÉRIO DO PLANEJAMENTOMINISTÉRIO DO PLANEJAMENTOASSESSORIA ECONÔMICA - ASSEC

State and Municipal Level

States and municipalities have their own law, which must follow the general guidelines of the federal law;

They have also their own fiscal autonomy, according to the Constitution;

Federal government has constitutional compulsory transfers to states and municipalities;

But, there are the non-compulsory transfers...

States and municipalities that surpass the 1% limit of their own “current liquid revenue” are blocked from receiving non-compulsory transfers;

Actually, the states of São Paulo, Minas Gerais and Bahia are the ones that have the most advanced PPP programs.

Page 12: MINISTÉRIO DO PLANEJAMENTO Public Private Partnerships Fiscal Issues in Brazil MINISTÉRIO DO PLANEJAMENTO Cuernavaca, Mx, 26/11/2008 Seminário de Intercâmbio.

MINISTÉRIO DO PLANEJAMENTOMINISTÉRIO DO PLANEJAMENTOASSESSORIA ECONÔMICA - ASSEC

Projects

Institutional Framework

Law 11.079

Page 13: MINISTÉRIO DO PLANEJAMENTO Public Private Partnerships Fiscal Issues in Brazil MINISTÉRIO DO PLANEJAMENTO Cuernavaca, Mx, 26/11/2008 Seminário de Intercâmbio.

MINISTÉRIO DO PLANEJAMENTOMINISTÉRIO DO PLANEJAMENTOASSESSORIA ECONÔMICA - ASSEC

Projeto BR 116/324

BR - 324

BR - 116

Concession to rehabilitate, operate, maintain and make capacity improvements in 680km of a logistical corridor in the Northeast of Brazil;

Cross subsidy between the two roads;

BR-324: around 20.000 VPD (70% light vehicles), BR 116: around 5.000 VPD (20% light vehicles);

Page 14: MINISTÉRIO DO PLANEJAMENTO Public Private Partnerships Fiscal Issues in Brazil MINISTÉRIO DO PLANEJAMENTO Cuernavaca, Mx, 26/11/2008 Seminário de Intercâmbio.

MINISTÉRIO DO PLANEJAMENTOMINISTÉRIO DO PLANEJAMENTOASSESSORIA ECONÔMICA - ASSEC

Projeto BR 116 - Modeling Estimated investment around R$ 1,1 billion (around US$ 500 million),

throughout the concession period of 15 years;

Fixed base toll fare of R$ 0,035/km (or US$ 0,016/km);

Dualization of 84km of lanes dependent on service levels;

Road upgrading works: Initial emergency recovery (first 6 months);rehabilitation and third lanes (first 5

yeras); Routine periodic maintenance; Dualization;

Operation services: Toll collection; Traffic monitoring and control; Mechanical and medical assistance to road user

Page 15: MINISTÉRIO DO PLANEJAMENTO Public Private Partnerships Fiscal Issues in Brazil MINISTÉRIO DO PLANEJAMENTO Cuernavaca, Mx, 26/11/2008 Seminário de Intercâmbio.

MINISTÉRIO DO PLANEJAMENTOMINISTÉRIO DO PLANEJAMENTOASSESSORIA ECONÔMICA - ASSEC

Project BR 116/324 – What Happened?

Project turned into a pure concession;

Many innovations colliding with the 2nd auction of public federal roads. Ex: Participation of foreign investors; Allowance of non engineering participants and subprocurement; New toll scheme (end of heavy truck subsidy); The “service” approach; Dualization based on service levels;

Project near sustainability combined with low toll fares (R$ 0,035/km or US$ 0,016/km);

Page 16: MINISTÉRIO DO PLANEJAMENTO Public Private Partnerships Fiscal Issues in Brazil MINISTÉRIO DO PLANEJAMENTO Cuernavaca, Mx, 26/11/2008 Seminário de Intercâmbio.

MINISTÉRIO DO PLANEJAMENTOMINISTÉRIO DO PLANEJAMENTOASSESSORIA ECONÔMICA - ASSEC

Pontal Project Irrigation project located in

Petrolina, PE, in the Valley of the São Francisco River;

Total area of 33.000 hectares, of which 7.717 irrigated;

40% of the infra-structure already built by the public sector;

Region already exports, annually, US$ 100 million in fruits;

Logistical chain prepared for exports;

Project is part of the PAC.

Page 17: MINISTÉRIO DO PLANEJAMENTO Public Private Partnerships Fiscal Issues in Brazil MINISTÉRIO DO PLANEJAMENTO Cuernavaca, Mx, 26/11/2008 Seminário de Intercâmbio.

MINISTÉRIO DO PLANEJAMENTOMINISTÉRIO DO PLANEJAMENTOASSESSORIA ECONÔMICA - ASSEC

Projeto Pontal - Modeling Water availability of 7,8 m3/sec;

Individual contracts for the operation of infra-structure and agribusiness, but they are awarded to the same consortium or individual winner that must be an agribusiness operator;

Bid evaluation focus on integration of small farmers that are chosen by the agricultural operator;

Tariff to end user based on amount of irrigated land and water delivered;

Term of 25 years and public payments set for the auction at a maximum of R$ 208 million (R$ 113 million on PV or US$ 50 million) during that period on a scale given by the government;

Expectation of 20.000 jobs created.

Page 18: MINISTÉRIO DO PLANEJAMENTO Public Private Partnerships Fiscal Issues in Brazil MINISTÉRIO DO PLANEJAMENTO Cuernavaca, Mx, 26/11/2008 Seminário de Intercâmbio.

MINISTÉRIO DO PLANEJAMENTOMINISTÉRIO DO PLANEJAMENTOASSESSORIA ECONÔMICA - ASSEC

Pontal Project – Public Payments Public payments conditioned on:

10% on availability; 40% on land occupation; 50% on performance, after the land is fully occupied.

Page 19: MINISTÉRIO DO PLANEJAMENTO Public Private Partnerships Fiscal Issues in Brazil MINISTÉRIO DO PLANEJAMENTO Cuernavaca, Mx, 26/11/2008 Seminário de Intercâmbio.

MINISTÉRIO DO PLANEJAMENTOMINISTÉRIO DO PLANEJAMENTOASSESSORIA ECONÔMICA - ASSEC

Financing in Brazil and the Credit Crunch

BNDES is the main source of financing for infrastructure projects in Brazil (US$ 30 billion disbursed in 2007);

Normally, concessions have pre-approved lines of credit of 70% of the value of the investment;

In less developed regions, this amount may be up to 80%;

Addionally, pension funds in adition to SOEs may have up to 80% (90% in less developed regions) of the value of the investment in PPP projects, either through equity or debt;

The FI-FGTS is another option, a fund of US$ 7,7 billion that can provide up to 85% of participation, either through equity or debt in infrastructure projects in selected areas (Transport – except for airports –, sanitation and electricity).

Finally, there are Constitutional Development Funds for the North, Northeast and Center-East Regions.

Page 20: MINISTÉRIO DO PLANEJAMENTO Public Private Partnerships Fiscal Issues in Brazil MINISTÉRIO DO PLANEJAMENTO Cuernavaca, Mx, 26/11/2008 Seminário de Intercâmbio.

Thank You.

Fernando Pimentel

Ministério do Planejamento, Orçamento e Gestão

Tel: +55 61 3249-4070/4593

Fax: + 55 61 3321-8084

E-mail: [email protected]