    Greater Mekong Subregion Economic Cooperation Program14th Meeting of the GMS Subregional Transport Forum

    Country Report on Priority Transport

    Projects between 2008 and 2012

    The Peoples Republic of China

    Nanning, Guangxi Zhuang Autonomous Region, thePeoples Republic of China

    2-3 December 2010

    Projects included in the Vientiane Plan of Action

    . Roads

    . Ports/Airports

    The views expressed in this paper/presentation are the views of the author and do not necessarily reflect the views or

    policies of the Asian Development Bank (ADB), or its Board of Governors, or the governments they represent. ADB does

    not guarantee the accuracy of the data included in this paper and accepts no responsibility for any consequence of their

    use. Terminology used may not necessarily be consistent with ADB official terms.

  • 8/8/2019 STF-14 Appendix 5B PRC

    2/13

    2

    . Roads

    1North-South Economic CorridorInternational Mekong River Bridge

    MOU among PRC, Lao PDR and Thailand

    A 50-50 cost sharing between PRC and Thailand

    Detailed design Completed in June 2008

    A grant from Thailand of about $1.2M

    ADB assisting in procurement of process for civil

    works

    Commenced in February 2010 & expected to be

    completed by 2012

  • 8/8/2019 STF-14 Appendix 5B PRC

    3/13

    3

    2. Western Yunnan Roads

    Development Project II (longling-ruili)

    Longling

    Ruili

    Estimated cost: 1,426 million USD

    Included in the ADB RCOBP for GMS (for aloan of $ 250 M under the 2010 pipeline) and

    COBP for PRCNegotiating meeting on ADB loan ended&Agreement on loan expected to sign in April,2011

    Feasibility study approved in Oct. 2010, and theconstruction will commence by the end of 2010.

  • 8/8/2019 STF-14 Appendix 5B PRC

    4/13

    4

    3Dali-Lijiang Road Upgrading

    Estimated cost: 2,400 million USD

    Financed by PRC government

    Commenced by the end of 2009

    4 years period

    15% investment finished by Oct 2010

    Lijiang

    Dali

    4Baise-Debao-Longbang Expressway

    Estimated cost: 1,016 million USD

    Financed by PRC government

    To be implemented by two sections: Baise-Debao-

    Jingxi section started on September 25, 2009; Jingxito Longbang to be started in 2010

  • 8/8/2019 STF-14 Appendix 5B PRC

    5/13

    5

    5Hechi-Baise Expressway

    Estimated cost: 2,012 million USDFinanced by PRC government.

    Feasibility study report completed

    To be started in 2010

    Hechi

    Baise

    6Preparation for signing the tripartiteMOU among PRC, Lao PDR and Thailand

    for the exchange of traffic rights along the

    north-south economic corridor

  • 8/8/2019 STF-14 Appendix 5B PRC

    6/13

    6

    MOU Discussion held in August 2010 among

    PRC, Lao PDR and Thailand for the exchangeof traffic rights along the North-South

    Economic Corridor with the assistance of ADB

    The MOU expected to be signed in 2011

    7Preparation for convening of the Third JointMeeting of GMS National Facilitation Transport

    Committee

    The Third Joint Meeting of GMS National Facilitation

    Transport Committee held in Vientiane on June 17,

    2010

  • 8/8/2019 STF-14 Appendix 5B PRC

    7/13

    7

    8

    Fangcheng

    Dongxing (54km)

    To be completed by 2013

    To be financed by PRC government

    Estimated cost: 376.5 million USD

    Preliminary design approved

    Construction started in April, 2010

    9Nanning-Baise (188 km)

    Started in June 2005 and completed in Dec. 2007

    between Greater Nanning (Tanlou City) and Baise City

    Assisted by ADB under the Guangxi Roads

    Development II project (Loan No. 2094

    Baise

    Nanning

  • 8/8/2019 STF-14 Appendix 5B PRC

    8/13

    8

    . Ports/Airports

    1Mengzi Airport Upgrading

    Estimated cost: 40.3 million USD

    Project application submitted to State Council

    for approval

    Project Assessment in progress

  • 8/8/2019 STF-14 Appendix 5B PRC

    9/13

    9

    2

    Nanning InternationalAirport Improvement

    Estimated cost: 126 million USD

    Financed by the PRC government

    Upgrading project for flight area completed inSeptember, 2009 with budgetary estimate of 94million USD

    Project proposal for the new main airportbuilding and its necessary accessories approvedin August, 2010

    3Guilin International AirportImprovement

    Estimated cost: 90 million USD

    Financed by the PRC government.

    Upgrading project for A380 type airplane started in September, 2008

    56% investment completed

    Upgrading project for the new main building to be completed in 2020

  • 8/8/2019 STF-14 Appendix 5B PRC

    10/13

    10

    4Improvement and Maintenance ofNavigation Channels along the

    Lancang-Mekong River

    Myanmar

    Yunnan

    VietnamLaos

    Thailand

    Cambodia

    Quadripartite Agreement on Commercial

    Navigation signed by PRC, Lao PDR, Myanmar

    and Thailand in April 2000

  • 8/8/2019 STF-14 Appendix 5B PRC

    11/13

    11

    the Upper MeKong River Navigation Channel

    Improvement Project with a grant of $5M by

    PRC government

    Needing financial assistance for further improvement

    and maintenance

    At the 13th GMS MinistersMeeting held in Dali, China

    proposed that ADB work out a strategic planning for

    water transport.

    ADB requested to expedite this process

  • 8/8/2019 STF-14 Appendix 5B PRC

    12/13

    12

    5

    Technical Investigation of RedRiver for Subregional Transport

    A technical investigation in 2011 proposed by

    concerned provinces in PRC (Yunnan province)

    and VietnamLao Cai Province

    6The second bridge on the RedRiver beween Hekou and Lao Cai

    Completed in Sept.2009 and Co-financed by

    PRC and Vietnam

  • 8/8/2019 STF-14 Appendix 5B PRC

    13/13

    13

    7Preparation of CBTA implementationManuals for the pilot border crossing of

    Mohan to Boten

    MOU on the initial implementation of CBTA at Mohan-

    Boten signed by PRC and Lao PDR in September 9, 2009ADB requested to assist PRC and Lao PDR to draft aCBTA implementation manual for the border crossing ofMohan-Boten