Project Management Tools for Modern Project
and Portfolio ManagementVladimir Liberzon, PMP
Peter Souza Mello, PMP
Victoria Shavyrina, PMP (Spider Project Team)
Session n# PMT01
Ferramentas de Gerenciamento de Projeto para uma Gestão Moderna de
Projetos e Portfólios
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Introdução
• Nesta apresentação iremos discutir o uso de técnicas e ferramentas que são utilizadas em gerenciamento corporativo de projetos ao redor do mundo.
• Questões durante a apresentação são bem vindas!
2
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
3
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
4
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
5
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
6
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
7
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
8
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
9
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
10
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
11
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
12
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Cálculo de Desperdício:recurso ativo
x ocioso
R$ 154.56028 dias
13
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Otimização de Cronograma
=Redução doDesperdício
R$ 138.00025 dias
14
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Economia de11% ao
tratar dados de custo
adequadamente
15
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
16
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Múltiplas EAPs (WBS)
• Atividades sem atribuição de pacotes:
17
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Múltiplas EAPs (WBS)
• Atividades com EAP por “entregáveis”
18
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Múltiplas EAPs (WBS)
• Atividades com EAP por “responsabilidade”
19
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
20
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
21
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
22
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
P a s s o s
• Identificação, seqüenciamento e estimativas sem restrições de recursos (PERT/CPM)
• Detalhamento baseado em restrições de recursos (nivelamento por recursos // corrente crítica)
• Identificação do caminho crítico real (task-critical-path / resource-critical-path) e folgas adequadas para atividades de projetos.
23
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
P a s s o s
• Identificação de requisitos financeiros, materiais e equipamentos para qualquer período de tempo
• Identificação de recursos renováveis e seus tempos de aplicação
• Análise de riscos e desenvolvimento de cronograma compatível com a parametrização dos riscos
24
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
P a s s o s
• Criação de mecanismos de medida de performance
• “Forecasting” de análise de performance para os parâmetros principais
• Registro de alternativas de projeto(aceitar e respeitar o acaso)
25
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
CPM x CRR• O método do Caminho Crítico é idêntico em todos
os pacotes de gerenciamento de software e todos devem propiciar os mesmos resultados se garantidos a mesma data de início, durações e calendários (CPM)
• Cronogramas por Restrição de Recursos (CRR) possuem diferentes mecanismos e aquele pacote que oferece o melhor resultado na otimização de um cronograma pode representar ganhos e economias aos seus usuários.
26
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Cronogramas por Restrição de Recursos (CRR)
• O pacote Spider Project Professional explora alternativas matemáticas com restrições de materiais, recursos e finanças para cumprir diferentes objetivos de projeto: redução de custo, garantia de prazo, utilização de recursos compartilhados, estabilidade de datas e reservas, entre outros.
27
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Cronograma sem restrições
• Para uma correta aplicação de CPM sem o detalhamento de recursos é necessário que se tenha recursos ilimitados.
• Exemplo: O recurso R1realiza atividades emparalelo (atividades 2 e 5)
28
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Cronograma com restrições
• Com este mesmo cronograma baseado em restrições, a atividade 3 deixa de ser crítica e a atividade 5 passa a pertencer ao caminho crítico, denominado Caminho Crítico do Recurso ou “corrente crítica”.
29
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
CRR e Corrente Crítica
• Embora muito similar, Cronogramas por Restrição de Recursos diferem da tradicional “Corrente Crítica” por que também considera fluxo financeiro e produção de recursos renováveis e não renováveis como fatores determinante do seu resultado.
• CRR são usados na Rússia desde os tempos da guerra fria e só se tornaram públicos na década de 90.
30
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
31
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Critérios de Sucesso em Projetos
• Tradicionalmente se estabelece com meta de projeto a sua entrega no prazo e abaixo do orçamento.
• Projetos orientados ao negócio podem desenvolver o “foco no lucro” e não o “foco no custo”
32
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Critérios de Sucesso em Projetos• Trump Tower em Chicago é
uma demonstração de “foco no lucro”:– Projeto + LONGO– Projeto + CARO– Projeto + LUCRATIVO*
*A opção é ter negócios já funcionando durante sua construção.
http://en.wikipedia.org/wiki/Trump_International_Hotel_and_Tower_(Chicago)
33
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Critérios de Sucesso em Projetos• A análise e otimização de
um cronograma em um projeto assim leva em conta os mecanismos de financiamento e também as previsões de faturamento com entregas parciais.
http://en.wikipedia.org/wiki/Trump_International_Hotel_and_Tower_(Chicago)
34
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Critérios de Sucesso em Projetos
• O caixa deste projeto é insuficiente para aproveitar os recursos disponíveis.
35
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Critérios de Sucesso em Projetos
• A falta de dinheiro em caixa pode obrigar atrasar o projeto.
• O lucro esperado é
de USD 219.077,00
36
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Critérios de Sucesso em Projetos
• Um empréstimo pode garantir o cumprimento da meta inicial.
• Sem caixa, o projeto atrasa até ter novas receitas.
37
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Critérios de Sucesso em Projetos
• O desempenho cai de:USD 219.077,00 para USD 193.724,96
38
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Critérios de Sucesso em ProjetosRealizar um empréstimo ou desperdiçar USD 25.000,00 ?
A decisão apropriada pode pagar por todo o esforçode planejar, em especial quando consideramos o
Gerenciamento de Portfólios.
39
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Análise de Risco eGerenciamento de Projetos por
Probabilidade de Sucessos (SDPM)
40
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Por que análise de riscos ?
• Nossa experiência em projetos demonstra que projetos baseados em cronogramas determinísticos tem baixa probabilidade de sucesso.
• A modelagem computacional de cronogramas com a análise de riscos pode ampliar a probabilidade de sucesso.
41
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Simulação de Riscos
• A simulação de riscos pode ser baseada em simulações de Monte Carlo ou usar três estimativas, como veremos a seguir.
42
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Simulação de RiscosEstimativas em 3 pontos
• Dados de projeto (duração, volumes, custos, etc) são coletados com o uso de três estimativas: - otimista, pessimista e mais provável.
• Eventos de risco são selecionados com base a “rankings” utilizados em análise qualitativa de riscos.
43
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Simulação de RiscosEstimativas em 3 pontos
• Cenário Otimista: – Contém eventos cuja probabilidade excede 90%
• Cenário Mais Provável:– Contém eventos cuja probabilidade excede 50%
• Cenário Pessimista:– Contém eventos selecionados
44
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Simulação de RiscosEstimativas em 3 pontos
• Cada cenário pode conter atividades e custos adicionais, além de empregar diferentes recursos e calendários.
• O planejador tem como resultado três diferentes cronogramas, com custos, materiais e datas para os principais marcos de projeto.
45
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
06/08 07/08 08/08 10/08 03/09 06/09
Parâmetros desejados
• A definição das probabilidades de se alcançar diferentes resultados permite se fixar custos e datas finais desejados (metas de projeto)
06/08 07/08 08/08 10/08 03/09 06/09
46
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
06/08 07/08 08/08 10/08 03/09 06/09
Probabilidade de Sucesso
• Para a meta negociada (cliente/patrocinador/equipe) temos uma probabilidade de ocorrência, que denominamos “probabilidade de sucesso”.
06/08 07/08 08/08 10/08 03/09 06/09
47
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
06/08 07/08 08/08 10/08 03/09 06/09
Buffers/Reservas
• A diferença entre o cronograma entregue para a equipe (otimista ou provável) e a data fixada como meta estabelece o buffer do projeto.
06/08 07/08 08/08 10/08 03/09 06/09
48
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Cronograma Crítico (exemplo)
• Existem reservas de custos, materiais e tempo que são calculados não somente para o projeto como um todo, mas também temos o registro de reservas comparados ao cronograma de trabalho.
49
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Tendências de Probabilidade de Sucesso
• A melhor forma de medir a performance de um projeto é estimar o que está acontecendo com a probabilidade de sucesso.
• Se ela aumenta, isso significa que as reservas estão sendo gastas abaixo do planejado.
• Se ela diminui indica que a performance não é adequada.
50
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Tendências de Probabilidade de Sucesso
51
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Tendências de Probabilidade de Sucesso
• Tendências de Probabilidade de Sucesso não refletem apenas performance de projeto (como é o caso de valor agregado) mas também por diversos elementos ao redor do projeto.
52
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Tendências de Probabilidade de Sucesso
Consideramos – assim – que a tendência de probabilidade de sucesso é a principal
ferramenta integrada de análise de performance de projetos.
53
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Tendências de Probabilidade de Sucesso
• Pode ser utilizada como único indicador de performance para a alta direção pois é suficiente para estimativas de performance e tomada de decisão.
54
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Success Driven Project Management
A aplicação do indicador de probabilidade de sucesso dá origem ao método russo Success Driven Project Management.
55
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Success Driven Project Management
Informações complementares sobre SDPM podem ser encontradas em http://www.gestaoeprojetos.com
Destaque: 5th Annual Conference of PMI College of Scheduling
– Apresentação dos princípios de SDPM por Russell Archibald (membro fundador do PMI)
– Detalhes por Vladimir Liberzon
56
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
57
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Ferramentas e Técnicas de GP Corporativas
• Devemos organizar dados de forma a apoiar a simulação de trabalho baseado em recursos em todo o Portfólio e com a aplicação de normas e padrões corporativos.
• Modelos Computacionais eficientes são baseados em livros de referência e bibliotecas (fragnets), garantindo maior nível de detalhe no planejamento e execução.
58
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Ferramentas e Técnicas de GP Corporativas
• Devemos calcular Cronogramas por Restrição de Recursos para cada projeto e o portfólio.
• Devemos garantir a aplicação de simulações de risco em projetos.
• Devemos selecionar critérios de sucesso que sejam compatíveis com os objetivos do negócio (pensamento no lucro e não no custo).
59
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Ferramentas e Técnicas de GP Corporativas
• Não há projeto sem incerteza e portanto devemos definir metas de projeto com probabilidades razoáveis e um bom controle sobre reservas de contingência.
• Projetos podem ser controlados mediante a análise da probabilidade corrente de sucesso em função das metas, de forma que se tome ações corretivas para probabilidades negativas.
60
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Contact InformationName: Peter Berndt de Souza Mello, PMPEmail: [email protected] // [email protected]
Phone: +55 16 8163-3903 // 61 3244-2510 ** Ribeirão Preto ** Brasília **
www.spiderproject.com.br
Session #: PMT01
61
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
COMPLEMENTOS
• A versão a seguir inclui slides com explicações complementares relacionados aos mapas mentais utilizados no evento.
62
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Project Management Tools for Modern Project and Portfolio Management
Vladimir Liberzon, PMP
Peter Souza Mello, PMP
Victoria Shavyrina, PMP
Spider Project TeamSession n# PMT01
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
64
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Parte 1
Requisitos de Sistemas de Gerenciamento de
Projetos Corporativos
65
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
66
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Requisitos de modelos computacionais para projetos e portfólios
Deve ser baseado em padrões corporativos.(dicionários, bancos de dados e bibliotecas)
Deve calcular cronogramas baseados em restrições de recursos levando em consideração limitações relacionadas a recursos humanos, materiais, fluxos de caixa e dependências externas.
67
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Requisitos de modelos computacionais para projetos e portfólios
Deve considerar prioridades entre recursos, atividades, fases e projetos.
Deve simular gastos e faturamentos para permitir o gerenciamento adequado de fluxo de caixa entre projetos em um portfólio.
68
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
69
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Requisitos de modelos computacionais para projetos e portfólios
Deve permitir o planejamento de uso de recursos com base a suas habilidades
Deve calcular a “corrente crítica” com base aos diversos tipos de recurso
Deve simular riscos e incertezas de projeto
70
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Requisitos de modelos computacionais para projetos e portfólios
Deve prover a alta gerencia com informações integradas que reflitam não apenas a situação atual, mas também tendências e performance do portfólio para a tomada de decisão.
Deve manter históricos de projeto/portfólio
71
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Parte 2
Dados(informações)
72
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
73
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Organização de Dados
• Sistemas coporativos de gerenciamento de projetos tem requisitos vitais para uma implementação adequada
• É necessário garantir que …
74
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Requisitos de Dados
• Os custos de projetos tem uma estrutura consistente entre cada projeto (uso dos mesmos componentes de custo)
• Contas de Custo devem ser a mesma em todos os projetos
75
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Requisitos de Dados
• A estrutura de codificação de fases, atividades, recursos e projetos sejam utilizadas em todo o portfólio
• Recursos compartilhados pertençam a um “pool” corporativo de recursos
76
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Requisitos de Dados
• Recursos do mesmo tipo dividem as mesmas características (atributos comuns de peso, unidade, volumes, etc)
• Atribuições típicas de recursos dividem as mesmas características (produtividade, custos, requisitos de materiais).
77
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Requisitos de Dados
• Processos típicos são modelados da mesma forma entre todos os projetos
• Estes itens e os requisitos de simulação de performance definem as estruturas de dados necessárias e algumas distinções serão vistas quando necessário.
78
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
79
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Estrutura de Dados• Os elementos de qualquer modelo
computacional de projeto são:– Atividades de Projeto;– Dependências entre atividades;– Recursos e sua aplicação;– Calendários e Custos;– Estruturas Analíticas de: Trabalho, Recursos e
Custos.
80
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
81
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Dados de Atividades• Normalmente atividades de projetos são
caracterizadas por suas durações.
• Além disso, é freqüentemente necessário se estabelecer o volume físico de trabalho correspondente a atividade.
82
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Dados de Atividades
• Volumes de atividades podem ser medidos em metros, em toneladas, unidades, percentuais, horas planejadas ou qualquer outra unidade.
83
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Dados de Atividades
• Diferente da duração, o volume de uma atividade não depende do recurso atribuído.
• Uma atividade que descreva uma obra civil, um pedaço de software, um documento necessário por sua unidade de volume (m2, caso de uso, unidade) pode ser aplicada em um ou vários projetos.
84
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Dados de Atividades
• A duração desta atividade é então o RESULTADO da quantidade de recursos disponíveis, o volume a ser realizado e a produtividade esperada.
85
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Dados de Atividades
• A aplicação de VOLUMES permite definir os requerimentos de custo e materiais típicos por unidade (tijolos por m2 ou pontos de função por caso de uso).
86
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Dados de Atividades
• A base corporativa de dados pode então fornecer informações para cada projeto referentes ao uso de recursos típicos em função de produtividade ou índice de produção.
87
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Dados de Dependências• Normalmente é necessário se criar mais do
que uma dependência entre tarefas (início-início & fim-fim, por exemplo).
• Além dos “lags” positivos e negativos entre atividades, pode ser útil se criar “lags” baseados em VOLUMES (A solda entre tubos ocorre quando X tubos já foram desfilados; Os testes começam quando X casos de uso foram integrados).
88
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Dados de Recursos• Além de recursos individuais pode ser
necessário se estabelecer as equipes/grupos e também as habilidades/papéis
• Um “recurso-múltiplo” é um conjunto de recursos trabalhando juntos, como um time, um “carro com motorista”, um “computador com software”, etc)
89
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Dados de Recursos• Recursos são divididos em duas categorias:
– Renováveis (recursos humanos e equipamentos)
– Consumíveis (materiais e equipamentos aplicados)
• Deve ser possível se atribuir materiais a recursos definindo seu consumo e não apenas as atividades (consumo de gasolina em um automóvel, por exemplo)
90
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Dados de Recursos• Se diferentes recursos podem fazer um
mesmo trabalho então eles tem a mesma habilidade ou papel.
• Recursos com a mesma habilidade são substituíveis entre si, apesar de poderem ter produtividades diferentes realizando a mesma atividade.
91
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Dados de Recursos• Um recurso pode ser utilizado em diferentes
habilidades ou papéis.
• Para cada papel, um recurso pode ter uma produtividade específica e consumir materiais/custos de uma forma específica.
92
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Dados de Atribuições• Atribuir recursos a atividades exige a noção
de “equipe” – um grupo de recursos trabalhando em uma atividade juntos.
• Uma “equipe” pode conter recursos individuais, múltiplos e habilidades/papéis.
93
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Dados de Atribuições• Para a definição de trabalhos parciais é
necessário estabelecer tanto o percentual do recurso atribuído como sua quantidade.– O uso de “cargas” ou “percentuais de
aplicação” visto em alguns softwares não é suficiente pois para um projeto pode ser diferente ter dois recursos 50% do tempo do que ter 1 recurso 100% do tempo.
94
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Dados de Atribuições• Um recurso útil para otimização de
cronogramas é o registro de uso variável de recursos.– Exemplo: Defini-se que o recurso X será
utilizado com uma carga mínima de 40% e uma quantidade mínima de 3 unidades. Isso permite que uma atividade inicie com recursos parciais e receba novos recursos na medida em que eles estiverem disponíveis.
95
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
96
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Dados de Atribuições• Além de consumir materiais em uma
atividade (processo), em alguns projetos é necessário se calcular a produção de materiais, de forma com que possam determinar o fluxo de ações para atividades subseqüentes.
97
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Calendários• Uma ferramenta corporativa deve conter
mecanismos claros e detalhados para garantir a atribuição de calendários personalizados para:– Atividades– Recursos– Relacionamentos (dependências) e “lags”
98
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Dados de Custos• Normalmente não é suficiente definir custos
por atividades e recursos e é necessário se conhecer todos os gastos e receitas, o que se gastará com impostos, aluguéis, equipamentos e etc.
• Em alguns casos é necessário se conhecer taxas de retorno e câmbios de moedas
99
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Dados de Custos• Componentes de custo devem ser utilizados
de diversas formas para garantir um gerenciamento de custos adequado
• Deve-se expressar inclusive os desperdícios, como por exemplo o custo de equipamentos parados ou pessoal mobilizado sem atividades de projeto.
100
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
101
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Cálculo de Desperdício:recurso ativo
x ocioso
R$ 154.56028 dias
102
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Otimização de Cronograma
=Redução doDesperdício
R$ 138.00025 dias
103
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Economia de11% ao
tratar dados de custo
adequadamente
104
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
105
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Centros de Materiais, recursos e custos
• A tomada de decisão em nível de portfólio ou mesmo no projeto necessita diversas formas de se comparar a realização x previsões.
• Centros de custo, materiais e recursos permitem análises detalhadas de diversas faces de um mesmo projeto.
106
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Múltiplas EAPs (WBS)
• A reorganização de atividades em diferentes Estruturas Analíticas de Projeto facilitam a identificação e detalhamento do escopo além de diferentes tipos de relatórios e mecanismos de controle.
• Sugere-se pelo menos a construção de uma EAP baseada em entregáveis, outra em processos e uma terceira em responsáveis.
107
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Múltiplas EAPs (WBS)
• Atividades sem atribuição de pacotes:
108
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Múltiplas EAPs (WBS)
• Atividades com EAP por “entregáveis”
109
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Múltiplas EAPs (WBS)
• Atividades com EAP por “responsabilidade”
110
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
111
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Arquivos de Projeto
• Um sistema de gestão de projetos deve ser capaz de permitir a análise de cenários não apenas entre um cronograma principal e uma linha de base, mas em função de múltiplas situações (medições diárias, semanais e mensais; cenários de risco; cenários de alternativas, etc)
• Arquivos de projeto devem ser versionados.
112
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Livros de Referência (bancos corporativos)
• Um sistema de gestão de projetos deve possuir padrões para aplicação em todo o portfólio.
• Padrões devem incluir não somente processos e modelos, mas também estimativas (custo, prazo, recursos) de atividades típicas.
113
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
114
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Biblioteca de “Fragnets”
• Uma “fragnet” é um conjunto típico de processos que pode ser utilizado diversas vezes.
• A criação de uma “fragnet” permite a modelagem detalhada de situações de projeto e sua reaplicação com maior segurança em novos projetos.
115
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Biblioteca de “Fragnets”
• Em TI, as atividades habituais de levantamento de requisitos, arquitetura, desenvolvimento e testes baseados em um “caso de uso” pode ser uma “fragnet” reaplicada em um projeto com dezenas de casos de uso.
• Pesos e ajustes finos são feitos no conjunto, aproveitando-se do ganho em produtividade na preparação do plano inicial.
116
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Biblioteca de “Fragnets”
• Em engenharia civil, uma “fragnet” para a montagem de “um canteiro” pode conter os recursos mínimos em uma situação padrão e depois ser detalhada com base a volumes (tamanho do canteiro ou mesmo tipo de terreno).
• Uma “fragnet” contém:– Em situações típicas, quem faz o quê, em quanto tempo,
por quanto, em que condições, por quanto e com que materiais e métodos.
117
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Continuação
• O complemento segue os slides originais.
Clique aqui para retornar a Parte 3
118